UTILITIES, TRENCHLESS – BTS MEETING | SECTOR


Q&A Following their presentation to the BTS both Max Hepburn and Matthew Donnachie took questions from the audience.


The Q&A is edited for clarity, brevity and available space. The Q&A highlighted topics such as procurement strategies, machine selection risks, and the role of carbon in decision-making. While the project remains live and subject to change, its findings already demonstrate the growing importance of trenchless technologies in sustainable infrastructure delivery.


Q: Was embodied carbon considered as part of the assessment and scoring process when comparing bored tunnel and pipejacking methodologies? A: Yes. Embodied carbon formed part of the overall evaluation criteria and was included within the weighted scoring system. It was assessed alongside cost, programme, and other key factors.


Q: Was there a specific TBM requirement that led to moving away from certain areas? A: No specific TBM requirement or constraint directl drove such decisions. The alignment decisions were based on broader considerations.


Q: Would the bored tunnel option, with its greater storage volume, provide better mitigation of future flooding and CSO discharges? A: It does offer such potential benefit, however storage capacity was not the sole factor considered in the option selection process. The pipejacking solution was identified as the more cost-effective option while delivering same hydraulic performance. It also offered benefits in terms of reduced embodied carbon, the ability to use direct drives to more effectively target CSO locations, and the potential for a shorter overall construction programme. While there are advantages associated with increased storage, it was also recognised that a larger storage volume could result in greater volumes being released to the wastewater treatment works following storm events. Additional storage does not necessarily translate into a proportionate operational benefit. The preferred solution was selected based on a balanced evaluation of hydraulic performance, cost, carbon, constructability, programme, operational considerations, and delivery risk.


Q: Could the bored tunnel works be split into multiple contracts? A: The works could potentially be delivered through multiple contracts or as a single contract package. The approach will be assessed and determined in future stages.


Q: What are the anticipated pipe jacking drive lengths and diameters? A: They are expected to vary significantly, depending on site constraints and alignment requirements, ranging from approx. 120 m to over 1km in length, with 1.5m- 2.4m ID pipes, subject to hydraulic and operational requirements. Larger pipe diameters may become more challenging in certain ground conditions and could require additional construction measures or interventions. But upsizing benefits can be increased storage capacity, improved operational


flexibility, and greater cost efficiency, but must be balanced against construction and delivery considerations.


Q: How has risk of machine failure been considered? A: At this early stage, machine failure has not yet been analysed in detail. Once ground conditions are better defined the approach will aim to reduce interaction with existing structures and mitigate risks.


Q: Has a final decision been made between TBM and pipejacking? A: No final decision has been made. The project is in the optioneering phase, and further ground investigation (GI) and analysis will inform the final selection.


Q: Have you got any reaction from the public? What were the results of the consultation? Was stakeholder engagement and knowledge sharing considered in the evaluation? A: Yes, stakeholder engagement was a key consideration within the evaluation process. A primary objective was to identify solutions that would minimise disruption to the public while still delivering the required improvements to the wastewater network. Stakeholder engagement will continue to evolve and once a preferred option has been selected will be tailored to address specific impacts, concerns, and requirements of the solution.


Q: Since optioneering is a repetitive task and Artificial Intelligence (AI) has proven efficiency in these kinds of tasks, was it used? A: Digital scripting tools were used to support certain aspects of the optioneering process, specifically to develop and assess potential tunnel alignments. These scripts helped automate repetitive engineering tasks and enabled the efficient evaluation of multiple alignment options against defined design constraints. However, they were not based on AI but that technology could potentially support future optioneering and evaluation processes, particularly where large datasets or repetitive assessments are involved.


Q: Some of the drive lengths seem long and some of the pipe diameters seem small. How will tunnel safety be managed with smaller pipe diameters? Material removal? Ventilation? A: The presenters acknowledged that the smaller pipe diameters being considered, particularly those around 1.5m ID, introduce additional challenges in terms of access, muck-out, ventilation, inspection, and emergency intervention. However, these smaller diameters are only associated with the shorter drive lengths. The proposed diameters exceed minimum thresholds in PJA guidance.


November 2026


| 31


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45