TECHNICAL | SOFT GROUND – HS2 PROPLESS OPENINGS - BTS MEETING


Right: Steel profiles to be cast at the edges of the special segments, their openings to hold dowels and rods.


Below: Some of conduit assemblies for dowels and rods that are


match-fitted to the edge steel profiles in the special segments.


In one arrangement the main shaft sits on the upline main tunnel and the adjacent satellite ventilation shaft sits on the downline tunnel. In this arrangement shaft construction happens before TBM arrival. TBM passage through the shaft is facilitated by foam concrete infill. In the other arrangement, the main shaft sits in the


middle between the twin tunnels. From the shafts extends SCL tunnels – a stub tunnel with four ‘fingers’ (each 13m2


)


extending and connecting down to the tunnel crowns (two to each main tunnel). In this case the TBMs can come through the area first and then shaft and finger construction follows later, or vice versa, he said. However, this arrangement is more difficult to construct in water-bearing ground and in such cases the other arrangement is chosen. There are many different openings in the segmentally-


lined tunnels and they serve different purposes. ● Cross passages connecting horizontally between the two main tunnels, used for evacuation in case of fire or other incidents, and also used for systems equipment storage;


● Ventilation openings on top of the tunnels in the shaft areas, connecting to above fans for smoke control in the event of fire and temperature control in a stalled- train situation. The air volumes are substantial. These are large openings; and


Below: Stacked steelwork reinforcement assemblies prior to segments casting, one showing the edge placement of edge steel profile.


● Shaft passages to provide access for emergency services and located at approx 3km intervals along the route.


OPENING DESIGN Michael explained that design began in earnest with the Early Contractor Involvement (ECI) phase of the project,


in 2018, when the construction team outlined a set of requirements to the designers which aimed to: ● Construct cross passages and inverts concurrent while keeping the shafts and main tunnelling activities independent, which would be beneficial as timelines can change on large scale projects;


● Have flexibility to change construction sequences, whether working from the tunnel or from the shaft;


● Ensure cost efficiency was also a main driver as there are 129 connections.


● Facilitate groundwater mitigation schemes close to the connections, particularly at cross passages;


● Seek standardised solutions given there are so many openings and minimise temporary works as much as possible; and


● Reduce risk during installation and opening. Having introduced the project and the approach to


design, Michael handed over to Xavier to discuss it in more detail.


Design challenge, concepts Xavier presented a geological cross-section from West Ruislip to Greenpark and explained that this length – the NTW portion of the Northolt Tunnels – was the most advanced in construction progress on the HS2 London Tunnels. He added that it is also the most illustrative for discussing design as the ground conditions are more variable and challenging compared to NTE and Euston Tunnels, which are mostly in London Clay. The NTW longitudinal alignment passes through


geology comprising over-consolidated clay, sand layers and chalk. Cover to the twin tunnels varies from 10m-30m, from west to east. At some cross passage locations the groundwater pressures reach almost 4.5 bar. Consequently, the NTW section illustrates the governing principles of the openings design were determined. The first design objective was to maintain an


unobstructed cross-section inside the tunnel, enabling various construction activities to continue. These objectives led towards a propless solution for the large openings required to support the segments of the bored tunnels. The second objective was to use one support system.


The conventional approaches of the past would often rely on temporary frames or other temporary works to deal with the forces around the opening, followed by heavily reinforced concrete collars or other permanent structures around the completed connection. The question was whether we could combine temporary and permanent


12 | November 2026


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45