TECHNICAL | SOFT GROUND – HS2 PROPLESS OPENINGS - BTS MEETING


railway systems team wanted sufficiently large openings. In 3D monitory surveys, taken three months before the


works and one after the opening had been exposed, the observed deflections were within the scan tolerance, less than 10mm. The solution performed well. Dominik handed back to Michael to discuss how the


ventilation shaft, which is one reason for the shaft’s trumpet shape. A maintenance adit runs from the mid-level of the main shaft over to the ventilation shaft. Also from the main shaft, but at tunnel level, extends a cross passage over to the Downline tunnel. A key project objective was for shaft and tunnel works


to be done independently. The ventilation shaft joins the top of the Downline tunnel across three rings that are opened at their crowns by removal of segments – at the end of the process. Beforehand, excavation and construction works are undertaken in the shaft area above the tunnel – while works continue in the TBM drive below. Monitoring was carried out during excavation. A collar edge structure is cast on top of special segments already installed in the tunnel rings to frame the area of tunnel to be opened, last. The geometry involved transitions between different shapes and angles, including flanges and a change from a cross- shaped arrangement towards a rectangular form. Waterproofing termination details were installed


from above, including sheet membrane. The final cast produced the completed ventilation opening, after which the tunnel segments could be removed from below. In this arrangement the temporary opening size of the shaft-to-tunnel connection equals the permanent size. The permanent ventilation opening was around 28m2


execution of the opening works within the tunnel below the shaft has been performed. Similar works had to be undertaken at both the South Ruislip and Mandeville locations, but within the tunnel the creation of the opening in the crown was carried out in two different ways. At South Ruislip other construction activities were


ongoing within the tunnel and a method was used to permit tunnel traffic flow to continue. A crash deck was built and segments were lifted up and out through the shaft – after being core-drilled into smaller pieces. The whole activity took 16 days for the crash deck installation and removal, and eight days for coring and lifting. They believe it is one of the largest openings formed in a segmentally- lined tunnel so far. At Mandeville the tunnel was blocked with an exclusion zone, enabling core drilling and saw cutting, and then demolition of the segments with an excavator – all of which took nine days. A few core drills, saw cuts and a hammer seem simple


but that is exactly the point, Michael said. Early investment of time allowed the later opening works to be simple, safe and straightforward.


Cross passages, groundwater mitigation Out of the 129 openings, 108 are cross passages (2 x 54 openings). They were the main driver to initiate a mass production approach into the connection works. The cross passage construction cycle began with core


. The


drilling and securing the segmental pieces. The pieces were removed with an excavator. Sprayed concrete lining with steel-fibre-reinforced concrete followed, then sheet- membrane waterproofing and secondary lining with a travelling shutter system. For non-treated areas, mainly in London Clay, preparation


Above: Photo looking up at the finished tunnel-to- shaft connection.


Above right: View above the running tunnel of an advanced stage of the shaft works in preparation for opening up the connection.


Right: Late stage


construction work in the shaft, preparing the some segments for removal where surrounding special segments are acting as a strengthened frame without need for extra propping or support .


16 | November 2026


took roughly four days, excavation about 20 days, waterproofing about nine days and secondary lining about 17 days. Where AGF was used, about 38 days were added for drilling the freezing pipes, followed by around 50 days for freezing, plus a slightly longer excavation period because soil properties change once frozen. By early 2026 there had been 34 cross passages built, giving 68 openings using the open-set solution. AGF was used at 11 cross passages and segment design retained windows in the reinforcement arrangement to allow freezing pipes to be drilled through the concrete, improving durability. Six other cross passages were dewatered or depressurised: two from the surface and four from within the main tunnel. Deformations were low. In London Clay, the opening


deformations were around 15mm. Where AGF was used the ice pressure acted on the rings but maximum deformations were about 25mm, which was within design assumptions. In using special segments to facilitate propless opening at


the London Tunnels, plus the inter-ring connection elements and resin grouting activities, the cost was about three times that of a standard segment.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45