SOFT GROUND – HS2 PROPLESS OPENINGS - BTS MEETING | TECHNICAL


sections. Two TBMs were launched in early 2026 near the western end of the Euston package and will perform twin 7.2km-long drives to the centre of the capital to reach Euston Approaches, near Euston station. The drives are served by the Atlas Road logistics compound, which has a dedicated supply tunnel. Segmental lining is transported to the hub by rail. Along the London Tunnels route there are seven shafts and 52 cross passages, 34 of which had been built by the beginning of 2026, Michael said. He added that SCL and cross passage works were carried out concurrently with the TBM works.


Invert construction Other main work activities include invert construction in the Northolt Tunnels with about 54,000m3


concrete (SFRC) mix (C40/50), partially reinforced, is used with a modular steel panel formwork system.


Connections works Across SCS JV’s scope of works there are 129 openings where the segmentally-lined tunnel connects to other structures. In their permanent arrangement, these cross passages and other openings vary in their permanent sizes from of approx. 6m2


– 28m2 and are of nine different sizes


in varying geology. Michael commented that connections look neat and


of C40/50


concrete to be cast while TBM advances were underway, and this was made possible using an 88m-long bridge system. Michael said two main drivers for this approach to construction were time and logistics. The concurrent casting of the invert saving programme time while the flat concrete surface on the invert improves traffic, logistics and safety in the tunnel. Production rates depended on the shift system and by


the time of presentation a best day of 65m length of invert built had been achieved, and a best week of 314m.


Walkways Concrete walkways run along the tunnels and are of two types: smaller for maintenance and larger for emergency use. These call for further significant concrete activities – total volume of 57,000m3


of C20/25 – and using a


53m-long Bridgeform System to cast the walkways on each side of the tunnel while preserving a route through the centre, again giving time and logistics benefits. Subcontractor is MPD together with SCS JV. Each pour is about 35m in length with approx. 70m3


cast. Working at casting 280m-315m per week of both walkways on a 24/7 basis. By early 2026 about 25% of the walkways had been completed using two bridges and a third bridge was about to be added for the Northolt Tunnel works, Michael said.


Cross passage door frames Also related to the openings are sliding-door frame arrangements along the Northolt segmentally-lined tunnels. These are to facilitate later installation of 75 doors plus others in the shaft areas. Steel fibre reinforced


simple on outline drawings but involve many complexities to be achieved, even if on final design drawings they still look elegant with clean lines. Connections require a lot of thinking, he said. As such, along the bored tunnel route to facilitate the safe


construction of connections in sections with presence of groundwater the options were freezing, dewatering from either inside the tunnel or from the surface, jet grouting or foam concrete blocks or a combination of these options. The choice between them depended mainly on available surface space and groundwater conditions. But the choices also have some relation to scheduling and sequencing with main tunnel drives. The shafts have been designed and constructed in two different configurations in relation to the running tunnels.


Above: Longitudinal geological profile of Northolt Tunnel West (NTW) package.


Left top: Schematic of ring constructed of special segments at location of a future opening.


Left bottom: Drawing of special segments fitted with extra steelwork at edges for both strengthening and connecting rings (showing shears dowels and a prestressing rod).


November 2026 | 11


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45