SECTOR | UTILITIES, TRENCHLESS – BTS MEETING


remained technically possible but were considered less favourable owing to uncertainty regarding ground conditions and groundwater behaviour. Pipejacking emerged as the preferred technology in


many locations. The use of slurry microtunnelling machines offered continuous face support, effective groundwater control, reduced settlement risk, and proven performance in challenging urban environments. The team also referenced PJA and HSE guidance to justify the adoption of conservative design assumptions and appropriate safety margins.


DANA STEPS CASE STUDY The Dana Steps CSO area served as a detailed case study illustrating the complexity of the optioneering process. This site is located beside the River Severn and can only


Above: Views or urban use change with time, adding complications on available and accurate data for planning new drainage alignments.


The presenters provided several examples illustrating


how historical investigations influenced engineering decisions. At Burrs Field, historical records revealed the existence of a 19th Century lead works and a former shot tower. While not necessarily preventing development, these findings raised concerns over contamination, buried obstructions, and heavy metal deposits presenting added site constraints and complexities. A second example was a town centre car park, where


historical mapping revealed that a multi-storey car park had previously occupied the location before being demolished. Although no longer visible at the surface, the potential presence of buried piled foundations, reinforced concrete slabs, and other residual structures represented a significant construction risk, particularly for shaft sinking and other deep excavation works. Another site, adjacent to Shrewsbury Railway Station


revealed the existence of a previously forgotten tunnel linking the railway with a historic ironworks. This tunnel crossed directly above a deep brick sewer under consideration for intervention. Such discoveries highlighted the importance of thorough historical desktop studies during early project stages.


Selection of Trenchless Technologies The design team reviewed a wide range of trenchless methods for potential use across the project. Technologies considered included:


● Pipejacking ● Horizontal directional drilling (HDD) ● Auger boring ● Pipe-bursting ● Timber heading


Each method was assessed against expected ground


conditions, groundwater levels, buildability constraints, hydraulic requirements, and expected drive lengths. The team also completed preliminary assessments of potential ground movement impacts. Timber heading was quickly discounted because


anticipated granular soils below the water table posed unacceptable risks. Auger boring and pipe-bursting


30 | November 2026


be accessed via a narrow riverside path that is frequently flooded. Existing sewers lie at depths exceeding 10m and pass beneath critical infrastructure, including railway lines. Additional constraints included a listed prison building, retaining walls, highways, residential properties, industrial premises, an historic tunnel, and a nearby landfill site. Initially, 11 potential intervention routes were identified.


Following detailed evaluation, these were narrowed down to four pipejacking routes for further development. Bespoke solutions considered included secant piled walls, caisson shafts, reclaimed land platforms, cofferdams, pumping stations, and deep river crossings. The case study demonstrated the iterative and


creative nature of engineering optioneering. Ultimately, alternative pipejacking arrangements enabled the team to design out many of the most problematic construction activities altogether.


Option Evaluation Methodology The final part of the presentation focused on the structured evaluation methodology used to compare competing options. The team developed an assessment framework based upon Seven Trent Water options process, incorporating more than 50 individual factors grouped into eight principal categories. These included cost, programme, technical feasibility, operational performance, health and safety, stakeholder impacts, environmental performance, and strategic alignment. Each category was supported by detailed justifications


describing potential advantages and disadvantages. This ensured decisions were based on evidence rather than subjective preferences. Importantly, the process encouraged engineers to consider issues beyond conventional technical feasibility and safety, including regulatory requirements, community impacts, long-term operations, and environmental consequences. A scoring system ranging from 0 to 5 was adopted.


Scores from multiple reviewers were averaged to help reduce the influence of individual bias. Initially, all categories were weighted equally, with the option for the client to apply different weightings based on project priorities. The assessment process was intended to be collaborative, allowing the client to contribute their knowledge of operational, maintenance, and project- specific requirements where appropriate.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45