SOFT GROUND – HS2 PROPLESS OPENINGS - BTS MEETING | TECHNICAL


Victoria Road Ancillary Shaft connection The first large opening to be built using the special segments was on the NTE section of the project, at the existing cross-connection from the Victoria Road Ancillary Shaft (VRAS). Twin 9m-diameter TBMs would bore parallel tubes passing through the VRAS and protruding cross- connection zone, for the Downline and Upline tunnels, respectively. While that latter zone would be filled with foam concrete for the shield to pass through, beside the VRAS shaft, relatively little of it would remain and provide ground support afterwards. The client challenged the team to accelerate


FABRICATION AND QUALITY CONTROL The special segments were cast in the segment factory outside the normal carousel process. Standard segments usually move continuously through production stages but the special segments had a separate, dedicated static production area as their quantities were relatively small. The reinforcement cages look complex but once understood the factory did not find assembly unmanageable. The design included sufficient tolerance, and the cages could be assembled and placed into the moulds. The feasibility of the reinforcement and embedded steel


arrangement had already been checked in a 3D model, including the gaps between bars and steel elements. The client asked for proof that the segments could be cast properly. To verify concrete flow, test pieces were cut in two directions and inspected, showing that the concrete mix with 10mm aggregate flowed properly, with good quality and no obvious voids. Integrity testing demonstrated effective compaction around embedded items. For the NTW drives the segment supplier was Pacadar


UK, at the Isle of grain, and the steelwork was by SH Group. For the NTE and ET drives the segment supplier was Strabag UK, in Hartlepool, and the steelwork was by CP Technology, in Milan.


CONSTRUCTION


Installing special segments The special segments are installed as part of ring assembly by TBM. Installation involves inserting the dowels and tie rods, in some cases while the segment is being handled by the vacuum erector. Tolerances allow the elements to be fitted without excessive difficulty, even where there were several connections. Prestressing is applied directly after erection while the thrust rams still act upon the ring. With no packings used, the prestressing also activates friction between the segment faces. The shear dowels are far larger than standard connection dowels and have corrosion protection. Once installed, the annulus around the dowel is grouted, leaving a completed connection.


construction of the final cross-connection structure and openings to link the Upline tunnel to the VRAS. The challenge was how to move to a quicker single advance rather than perform the works by staged construction as had been planned. The shaft’s secondary lining was incomplete and would not contribute to support. Rather than introduce temporary works – which was not in plans and would have programme and H&S aspects, and possibly stiffness concerns – the local design of the Upline tunnel lining beside the VRAS was reconsidered. Extra connections were introduced between the existing special segments. The design team checked that with their contribution a larger opening could be formed without conventional internal propping. With the Upline TBM having passed beside the VRAS,


excavation began from the shaft towards the rings, exposing them as excavator operator stopped exactly where needed. The Upline TBM cutterhead was only a few metres ahead as the excavation was performed. When the rings were fully exposed by the approx. 11m-wide opening, they remained stable thanks to the special segments that were installed at the location in the Upline tunnel. On the other side of the excavation, through the concrete rings, TBM gantries were passing. The segments behaved well. No significant deflections were measured, and no significant cracking was observed. The open connection then had waterproof sheet membrane installed along with reinforcement and concrete casting could proceed.


South Ruislip and Mandeville ventilation openings The shafts at South Ruislip and Mandeville were the main shaft on the Upline tunnel and a satellite ventilation shaft as a top connection to the Downline tunnel. At South Ruislip, the Chiltern Railways Line is almost directly above the


Above: Drawings showing staged construction of the shaft connection to the crown of the running tunnel.


Far left: Schematic showing a close-up of the proposed shaft (brown) to tunnel connection. Inside can be seen where running tunnel segments are to be


removed, enabled by special segments acting as a strengthened frame and creating a propless opening.


Left: Photo inside the shaft looking down on the exposed rings of the running tunnel and adjacent works underway to construct the


structural support collar. November 2026 | 15


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45