HEALTHCARE VENTILATION
Managing critical systems is often a challenging task
Simon Everett, a Senior lecturer in the Built Environment at Wrexham University, discusses some of the challenges of managing ‘legacy’ AHU systems across the healthcare estate, and some of the key steps for healthcare engineers to consider to minimise the risks of such equipment failing.
Critical ventilation systems, i.e. those serving areas that cannot function safely without such systems (for a full list see HTM 03-01 a, paragraph 4.311
) in healthcare
premises, when designed, installed, and maintained correctly, help control the spread of airborne pathogens through the dilution and removal of contaminated air. Not all systems comply with current standards, and even some of those may not meet their design specifications – which may go unnoticed until their annual verification. For Estates teams, managing risks associated with legacy equipment is a significant and complex challenge. Assessing the condition of air-handling units (AHUs) regularly is important from a maintenance perspective, but is also crucial for effective lifecycle management, because early warnings can help avoid costly and sometimes catastrophic failure of the equipment, which in turn poses the risk of service interruption, infection control issues, and other safety considerations.
Competing with other capital funding requests NHS Estates teams are often competing with other capital requests, and often clinical needs trump infrastructure, but is this because of a lack of understanding at a strategic level, and what happens when infection rates in operating theatres soar, and Infection Prevention and Control (IPC) teams investigate the root cause? From an Estates perspective, ensuring that AHUs have been maintained to the correct standard is vital, then. The plant should be performing to criteria laid out in HTM 03-01, but this might not always be the case – particularly with respect to plant installed prior to the most recent guidance. There should be annual verification and performance testing conducted, with performance compared with the
A modern UCV theatre air-handling unit.
validation figures obtained at the time of installation and commissioning. The values measured must achieve a minimum of 80% of the original air-change rate (HTM 03-01b, paragraph 4.16). The HTM makes the point that systems nearing their end of life may reduce in performance: “it is to be expected that over the lifetime (typically 20 years) of a ventilation system its performance will gradually reduce...” (paragraph 24, part B). However, the HTM is clear that equipment that is not performing to the required criteria should not be used. In this instance, what options should Estates teams consider? In this article, we will discuss the pitfalls
facing Estates teams, focusing on critical ventilation air plant, and suggest strategies for managing capital budget expectations, IPC risks, and operational and compliance considerations.
Pragmatism or idealism? With no data specifying the number of AHU systems in hospitals at the end of (or nearing) their useful life currently publicly available, it’s difficult to arrive at an accurate cost of replacing or upgrading to condition B all units across the country. However, for Trusts that operate and maintain legacy AHU systems, it is likely there will be other backlog issues
for its buildings such as heating or fire compartmentation. Where there are life- critical safety implications (for example, fire protection), these will often trump less ‘visible’ – but potentially as critical – legacy plant such as AHUs because of perceived risk.
Understanding the backlog profile of
the estate should be a priority for Estates management teams, but often the correct methods are not employed. For Trusts in England, responses from the latest Estates Return Information Collection (ERIC) data2
indicate that approximately
41% of sites had been surveyed formally, and just over 20%, since 2018. The latter figure is significant, as this might indicate an established rolling programme. Those sites with up-to-date backlog data are likely to be much better informed on their position, and have a better understanding of where their assets are in their lifecycle. This doesn’t necessarily mean that there is detailed information for any AHUs on the site. For critical ventilation plant (as defined in paragraph 4.7 of HTM 03-01b), a key document in understanding current performance capability would be the annual verification report. This document will identify whether the equipment meets the requirements set out in HTM 03-01, and – crucially – where, and why.
September 2024 Health Estate Journal 67
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120