This page contains a Flash digital edition of a book.
requirement for large flat sites on which to locate these hospitals with a target site size of 30-35 acres. Te Ghana Ministry of Health had undertaken


to provide to NMSI six sites that were generally flat, measuring at least 30 acres and with highway and utility infrastructure to the boundary of the site. In late March of 2013 CampbellReith joined the design team in Ghana to review the sites, the local environment around each of the sites and commence the development of the masterplan into six localised development proposals. Te geographical landscape of Ghana does not


generally lend itself to large flat areas of land particularly in the six districts that had been identified for development. It became apparent from the site walkovers that the engineering masterplanning of these six sites would be a complex exercise and without the initial benefit of detailed topographic information the site reviews would need to be supported by a greater level of technical detail to assist the site masterplanning.


THE APPLICATION OF TECHNOLOGY Te team from CampbellReith were able to obtain a combination of georeferenced aerial photography, 1:50,000 scale topographical records and Satellite Lidar data for each of the six sites from a wide range of mapping sources. Together with GPS logs taken from the walkover surveys we were able to produce constraints mapping that identified each individual site area, its boundary, basic contours, vegetation, watercourses and existing infrastructure. Tis constraint mapping was used to locate the development masterplan within the site environment and then test it against the key criteria for development. Initial three dimensional assessments were


carried out on the principal earthworks required to support the development. Geological records were reviewed (including those held by the British Geological Society) to produce desktop reviews of the underlying geology and an assessment of the likely earthworks costs to undertake the development. Access and servicing could also now be considered and costed. Tis was all fed back into the masterplan which was tested and adjusted on a site specific basis. Working with the Architect we established maximum gradient criteria between buildings and around the site, replanned and restructured the movement strategy to mitigate for level changes and orientated the development to suite the topography and access arrangements. As a result, a number of the original site


allocations were either rejected by the team as being unsuitable for development or adjusted by agreement with the Ministry and local administrations to suit. Once sites had been finally approved for construction, detailed topographic, geotechnical and hydrological surveys were commissioned to confirm the initial design assumptions and enable detailed design to be undertaken. Geotechnical Investigations have been specified


to obtain the vital information on the underlying strata required to characterise the development site to the standards and codes applicable to the design. Te team also drew upon the expertise and testing facilities available within the local market


expertviewmagazine.com EXPERTVIEW SPRING 2015 43


Opposite and below: Te first three hospitals are currently under construction in Dodowa, Fomena and Kumawu


with knowledge transfer training being provided where necessary. Where rock has been encountered within the investigations we have worked with the team to make adjustments to the masterplan and layout to avoid uneconomic excavation and make best use of the firm foundation strata. Hydrological investigations have been carried


out as a desktop exercise to ensure that each development was initially suitably located and to avoid unnecessary conflict with rainy season flood flows. Subsequent physical borehole investigations have been carried out to determine the suitability and location of ground water for supply. Te first development site in Dodowa commenced early in 2014 and the building structures are now underway with a completion expected early in 2015. Two further sites have commenced full construction with a third in early preparation for commencement. One site in the Sekondi District remains


unidentified but we have now developed the expertise within the team to be able to undertake initial site reviews and advise on suitability remotely through desktop review and can within a very short timeframe respond with a wealth of environmental and topographical mapping. Te initial masterplan is now incorporated into


a digital 3D model for building and infrastructure layouts. Te model contains the constraints and variables of the developed design philosophy which can overlaid onto any specific site in question and assessed to understand the acceptability of the site for development. Site development planning can be undertaken principally as a desktop exercise and, only when suitability has been confirmed through the initial review, are the costly and often time consuming physical investigations undertaken. By using modern technology issues that would


normally be associated with a rural building projects can be overcome. Tis highlights the scope and productivity of smart city technologies, and demonstrates that modern advancements do not have to be restricted to highly populated areas. Indeed they can be used to provide infrastructural assistance to the areas that are most in need, even if they are remotely situated.


EV For more information go to www.campbellreith.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60