drawings commenced. Geotechnical investigation was also conducted. Record drawings of underground utility services at the site were sketchy and hydro-vacuum excavation was required to locate the services. An action plan was charted out to ensure completion of all foundation work under winter conditions. As soon as the ground thawed, site grading and compaction and concrete paving could proceed. Pergola installation, landscaping, tree planting and flower beds would be completed in April/May and the official opening in June. This indeed was to become an aggressive project schedule. Excavation and boring for cast-in-place


Excavation and boring for cast-in-place concrete piles started in the first week of January 2013.


25 July 2012 and tender documents were completed on 5 September2012. The pre-tender construction cost estimate


was $428,000, consisting of $210,900 of base design and $217,100 of options. The CCIVA had earmarked $300,000 for the project. Despite the substantial budgetary shortfall, it was decided to call bids for a base price and separate prices for optional items right away. This arrangement had worked well for minor work bidding, which was often unpredictable due to market conditions and opportunities. The bid acceptance period was extended from 30 to 45 days to provide additional time for the review of base bids and separate prices for contract award. In the meantime, CCIVA sought additional funding from government, not-for-profit organisations and private sector corporations. The Alberta Cancer Foundation (ACF) rose to the call and endorsed the project with a generous financial undertaking.


The bidding process On 17 September 2012, three contractors were invited to bid as scheduled. Two bids were received and opened on October 11, 2012. As the bids were examined, it was


surprisingly noted that the lowest bidder also submitted an offer to underwrite some the of construction costs. The bidder, Delnor Construction Ltd, together with sub- contractors and suppliers, had joined forces to make a generous donation to the project. The contract was subsequently awarded to Delnor. What was originally a project embarked upon by the volunteers at the CCI had become a reality through the joint efforts of a fruitful and collaborative relationship between the CCIVA, ACF, and Delnor. The next steps included preparation for long delivery material orders and shop


concrete piles started in the first week of January 2013. Underground utility services immediately posed major challenges. A layer of asphalt from the apron of the former loading dock was found 1.5 m below the site. Utility services under a feature wall were especially congested. A gas main was found directly under pile no.5, with water main, sewer drain and power cables close by. Hydro vacuum excavation and pile boring had to be conducted piece meal. Piling for the pergola was eventually completed on 5 April. Foundation design for the feature wall had to be changed to a hybrid of piles and grade beam. A power cable under the monument had to be relocated for its foundation. Following completion of all foundation work, site grading and compaction was undertaken. At this juncture the project was over two months behind schedule. As site grading and compaction


progressed nine existing trees started to show signs of distress. Project landscape architect submitted an assessment that ‘…varying degrees of damage has occurred to all the


‘Patients and staff enter and experience a new realm of holistic cancer care.’


IFHE DIGEST 2015


The was garden officially opened in September 2013.


73


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96