This page contains a Flash digital edition of a book.
STATION MODERNISATION & EQUIPMENT


The station over


With all the major civil engineering work now done, the team behind the complex Blackfriars rebuild can give themselves a huge pat on the back. The project’s leaders, including Network Rail’s project manager for Blackfriars Rob Lines, and Balfour Beatty Civil Engineering project director Chris Evans, briefed RTM on the challenges they’ve faced to get this far.


ost civils and stations projects on the railways involve working in restricted spaces and dealing with logistical challenges.


M


But few recent projects can match the Blackfriars upgrade for that sort of complexity, with work being done over the River Thames, over and next to live Tube and national rail lines, and busy roads.


But three years later, as Rob Lines, Network Rail’s project manager for Blackfriars, puts it: “It’s starting to look like the artist’s impressions – it’s really quite magnificent.”


The key parts of the upgrade have been the overhaul of the Underground station, platform widening and extensions to allow frequent


service on the Wimbledon/Sutton loop and for passengers from East Croydon. The station is also now ready to accommodate the full 12-car, 24 train-per-hour Thameslink services from 2018.


FCC’s Roger Perkins said: “Blackfriars is back on the Tube map: that’s made a big, big difference to our customers, and will shorten their journeys. It makes Blackfriars a more attractive proposition as a station to use, and what people are slowly waking up to is the fact we have this new south station. Along with Network Rail, we have started to really push this.


“Commuters love it; immediately, it’s 10 minutes knocked off their walking time to work, if they work south of the river. It’s also really perfect for Bankside: for Shakespeare’s Globe, and, further down the river, the South Bank attractions.”


He said 75,000 passengers used the new southern station entrance in March, double the December 2011 figure. He added: “I’m not sure if we realised it was going to be as popular as it is.”


Thameslink 12-car running and higher


passenger flows, a new station entrance on the south bank of the Thames, and major changes to track alignment, including shifting the through lines from the west side of the bridge to the east.


It has been a 24/7 worksite since early 2009, but now the ‘Thameslink baton’ is being passed over to the London Bridge team – hardly a small project itself, of course.


Passenger benefits


First Capital Connect, which has waited patiently as the work was being done, while dealing with the disruption as it affected passengers, drivers and staff, is thrilled with the results, now that the track is available again at nights and weekends. FCC can run eight-car trains at weekends, increase service frequencies, and offer a better weekend


68 | rail technology magazine Jun/Jul 12 Looking back


Reflecting on some of the major civil engineering challenges along the way, Chris Evans, project director for Balfour Beatty, spoke first about the need to isolate the live Underground lines at Blackfriars,


the Circle and


District lines, from the construction site.


This involved a solid steel, 350-tonne Track


Protection Structure (TPS),


which “effectively put the Underground tracks in a tunnel”, as Evans put it. The structure had to be put in place in 39 separate sections in April 2009, with each part slid along steel beams, because of the small size of the access available from above. Evans said: “It was a ‘steel shield’ completely hiding


the railway from us, while we demolished the station.”


Most of the old station was demolished during summer 2009, while the subway connecting platforms 4 and 5 was replaced by a temporary footbridge.


Thames


In December 2009, during a major Christmas- time track possession, the team undertook the so-called ‘bridge slide’, when the existing bridge was dismantled, removed and replaced with a new prefabricated structure that was slid into place in three days. Everything possible was done before the possession to ensure it went smoothly, with meticulous planning, as the team had only one shot to ensure it was a success – and all the subsequent works depended on it.


Evans said: “With the bridge slide, there was a massive sequence of events that all had to happen concurrently to allow the overall programme to move ahead.


Below: The track switch - before and after


THE


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92