Construction Site Layout and Housekeeping


The construction EMP will include a site layout showing the location of site compounds and main features of the site. Further site investigations will be required for the project. Prior to any intrusive investigation or construction work, all existing service plans would be consulted and a comprehensive service line location survey carried out in order to ensure that existing services are not disrupted. This would include radio detection, ground penetration radar and vacuum excavation where necessary.


41


A good housekeeping policy shall be applied across all construction areas throughout the construction period. This shall include the following requirements:


all working areas shall be kept in a clean and tidy condition


all site compound areas shall be non-smoking. Specific areas within the worksites shall be designated as smoking areas and shall be equipped with containers for smoking waste. These shall not be located at the boundary of working areas or adjacent to areas deemed sensitive to local residents, workers or visitors


open fires and burning of rubbish are prohibited at all times


radios (other than two-way radios used for the purposes of communication related to the works) and other forms of audio equipment (other than associated with safety mechanisms (such as reversing bleepers) shall not be operated on any worksite


site waste susceptible to spreading by wind or liable to cause litter shall be stored in enclosed suitable containers and waste shall be removed at frequent intervals and the site kept clean and tidy


static plant should have suitable drip tray protection


hoardings and boundary fences shall be frequently inspected, repaired and repainted as necessary adequate welfare facilities shall be provided for all site staff and visitors.


42


In addition, where working areas are within Flood Zone 2 or 3 additional measures shall be taken to minimise pollution risk during periods of extreme weather (i.e. flooding) by including:


the Contractor will be required to sign up to the Environment Agency „Floodline‟ flood warning service


Outline Code of Construction Practice. Version 3. Page 17


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61