5.4 Consultation Summary 78. A preliminary timetable for the consultation process is summarised in Table 1 below.
79.
From the publication of the SoCC to the finalisation of the Environmental Statement, all those consulted will have the opportunity to view and provide comments on the project.
Table
1.Consultation Activity and Time Plan Month/Period
November 2012 Consultation activity
East Anglia THREE Limited publishes a Scoping Report for the East Anglia THREE project, outlining known information on the site. This document provides environmental information referred to for the purposes of the Statement of Community Consultation (SoCC).
May 2013 August 2013 September 2013
Non-Statutory consultation with Local Authorities on the contents of the draft SoCC.
Statutory consultation on SoCC begins.
East Anglia THREE Limited publishes notice of the final version of SoCC in East Anglian Daily Times, the Eastern Daily Press, the Ipswich Star and Fishing News, on the East Anglia THREE Limited website and deposits SoCC in local libraries.
October 2013
Public Information Days and related events to coincide with, and provide statutory consultation on the East Anglia THREE Limited publication of the SoCC. These will be advertised locally and in the local press.
Spring/Summer 2014
Public Information Days and related events to coincide with publication of the PEIR. These will be advertised locally and in local press. Publication of this document will provide an opportunity for members of the public to comment on the project and form part of the statutory consultation on the project.
Summer/Autumn 2014 Winter 2014
Finalisation of Environmental Statement and Consultation Report, ready for submission of application to the Planning Inspectorate.
Submission of application to the Planning Inspectorate. Application will be published on the East Anglia THREE Limited project website and full details will also be available on the Planning Inspectorate website after submission.
http://infrastructure.planningportal.gov.uk/projects/eastern/
Report to Inform the SoCC September 2013
East Anglia THREE Offshore Windfarm Page 24
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41