STATION MODERNISATION All images courtesy Network Rail modernisation along the route.


“Between Bedford and Brighton, which is our core route for the upgrade, we have been carrying out a lot of work on platform lengthening in order for those stations to be able to deal with the new twelve car services. This has also involved moving overhead line gantries and moving signals so that we are free to extend the platforms.


“This work has particularly concentrated on the Midland Mainline between London St Pancreas and Bedford. Twelve car operation will be available in December 2011, with completion of KO1 in the summer of 2012.


“Key output two, the other half of the Thameslink project, centres around the remodelling, re-signalling and rebuilding of all of London Bridge station and associated infrastructure.


“This project is currently in a feasibility phase and that will be completed in November this year. What we are working towards at the moment is a scheme which is affordable within our budget whilst also delivering the desired output. These works will begin their implementation stage post 2012 and run for a number of years because this will be in effect a complete reconstruction of the infrastructure around London Bridge, both in terms of the station and the railway.”


Obviously a programme of this size will require the team to innovate on an almost daily basis to allow the project to finish on time and on budget.


“Blackfriars station has every kind of interface that you can possibly imagine along with the fact that some teams are working over a river whilst some are adjacent to road traffic, all the time whilst trying carry out


72 rtm


AutoTransformer System on the Midland Mainline


Cardinal Tower being demolished


this work and keep parts of the station operational.


“In terms of deliveries to the works at Blackfriars, we have been looking to bring in as many materials as possible by rail and river because obviously bringing


them in on lorries through central London is particularly difficult in terms of access.


“Apart from the logistical challenges, we are also constructing the new station over a Victorian bridge structure,


with the all the original ribs being retained but with new steelwork over the top. This means that we have to have a good understanding of the bridge’s structure and carry out the work in very controlled manner so that the bridge stays stable at all times.”


One of the main issues around carrying out the works at Farringdon station is the fact that both the Underground and mainline services have to be kept fully operational.


Oct/Nov 10


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100