Ultimately, this also meant that we could deliver a reduction in the operating deficit for Metro to the government.


“The upshot of this is that we have developed a twenty year asset renewal plan and now have a revenue support plan agreed with government for the next nine years, along with an agreed investment plan for the next eleven in total. This is really good news, as it means that we have secured sufficient funding for Metro for the long term and that funding is enough to allow us to invest in the network, to ensure that it maintained and improved on a planned and efficient basis.”


Work on the Metro network has now been ongoing for sometime now, with many different projects all running at the same time, including works to station, track asset, along with bridges and tunnels.


“From an investment point of view, work will now begin in earnest with the first part of this


Oct/Nov 10


being a blockade in February and March 2011, which will be the first time that we will have ever had a complete closure of all or at least part of the Metro network, to allow us to undertake engineering work.


“One of the main issues which we have faced in the past when we have wanted to undertake major engineering works was that we have only ever had a very short ‘wheels free time’ available to us because last train gets into the depot at around 1am and the first train leaves at around half past four.


“This initial blockade with occur between Chillingham Road and North Shields, lasting for about four weeks. This will allow us to carry out all of the engineering work which we think is necessary on that stretch of line, which includes things like cable renewals, permanent way renewals, work to embankments, cuttings and to the stations.


“This will mean that when we


come out of that blockade we will effectively have a new railway along that stretch of the network and that, apart from routine maintenance, we will not have to go back to that section for a long time.


“One of the issues which we had in the past with regards to maintenance was that we didn’t know enough about our assets and so part of this process over the next nine years will be accumulating that knowledge about our assets so that we can get to a position where we can predict what the optimum time will be to maintain and then to renew an asset. At the moment we are having to do this on a case by case basis and the section of line which we have concentrated the most on is one of the oldest.”


Given the current fragile state of funding around the transport sector, every organisation is looking to reduce its spending, whilst also ensuring that everything that is spent provides value for money.


“Ultimately we will be able to extract efficiencies because, firstly, we will carrying far less emergency repair work and far more planned maintenance and, secondly, we will be adopting more modern working methods, along with the benefits of having new assets and tools. This means that over time we will be able to generate more and more efficiencies as we go forward.


“With regards to maintaining efficiency on the refurbishment project itself, we have put a lot of effort into the planning and management of the work itself and have established a programme management office.


“This means that we will have a proactive process where we can check and challenge what the project managers are telling us, allowing us to monitor both physical and financial progress. When we do experience deviations to that we can take appropriate action, before it becomes a problem.”


rtm51


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100