STATION MODERNISATION


crash deck to protect the trains underneath.


“From the north access deck, we also have substantial access ways running down the valley gutters - both in between and to the side of both barrels - and we run the materials up and down there on two small temporary railway tracks which we have built on the roof.”


All of the enabling works have now been completed and the team has now spent a number of months stripping out the southern end of the roof.


“This has involved grit blasting it back to the steel work and we are now at the stage where we have begun to fix some of the new steel to the first four bays on the roof which will take the new glazing.


“The first part of this project is inevitably going to go slower because there is a learning curve which we have to go through, but also from a practical point of view it is the furthest distance to carry the materials because of the its position. This means that we expect that, as the work proceeds, each bay will become faster and faster to fit out and we hope to have the first four bays complete before Christmas.


“We hope then to move onto the second four bays and, at some point next year, we will be able to reveal the work which has taken place as we move the deck down to the work on another section. We’re looking forward to that day because it will be the first time that the passengers will be able to see some completed evidence of the works which have taken place on the roof. We hope to have this completed sometime around the end of 2011.”


The third package of work is also in the main train shed and has centred around the


68 rtm


refurbishment of the platforms, one by one.


“This includes installing new platform edges and tactile strips along with resurfacing the platform but more critically it has included putting in new lift and escalator pits along with the steel work for the new passenger bridge. Following just over another six weeks of work, we will reopen that platform and begin the process on the next island platform, with these works continuing for about a year. We will then begin work on the platforms either sides (One and Eight) and hope to have all of the work done to the platforms completed by 2011.


The next package of work is a part which most of the public will never see but has been a major civil engineering project in its own right. This work will facilitate all of the back-of-house operations at the station and will allow for seamless operation, out of the public eye.


“In the future all of the retail in the station, offices and on-board


catering services will be fed by a series of back-of-house passage ways and tunnels, which will all feed into an area called the shared service yard. This is a large underground service bay which will be capable of taking five lorries at any one time as well as having space for rubbish compacters and other ancillary equipment.


“From this yard there will eventually be a service road which will find its way back up to surface level and out onto Goods Way, just next to the Goods Way tunnels.”


Other packages include a major switch over of utilities which was completed early on in the project.


“This involved putting all of into one big duct and moving it about five metres sideways to enable us to build the new concourse. In cost terms it was very small but in importance terms, it was crucial to the project.”


This leaves only packages six and seven. The former includes all


Oct/Nov 10


of the enhancement work taking place on the western side of the station.


“This includes the new western concourse which is considered to be the jewel in the crown and will become an iconic building. It is a fabulous piece of architecture and the best piece of rail architecture which the country has seen for some time.”


Other works in package six include works to the western range building which, once complete, will reveal a beautiful piece of Victorian architecture which has been obscured from public view since the 1960s.


“Package seven is the last piece of work which we shall do which will happen after the Olympics and is the creation of a new public square outside of the southern end of the station.”


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100