The point of the Marine Warranty is to insure against loss of an asset. In this case, the loss of a large hull block or a topside module for an oil rig could have catastrophic repercussions for the delivery of the overall project as well as financial loss of the asset. For example, a topside module for a FPSO could cost $100’s million and take years to fabricate, if that one module is lost at sea or damaged it will ‘set back’ the project considerably.
There may therefore be a requirement either from the main shipyard themselves or the shipyard customer (Ship Owner) to have a warranty to transport the block from remote sub-contractors to the main yard. The block needs to be lifted and loaded onto the transport barge or ship and then travel by sea to arrive at the main yard, ‘just in time’, for it to be made ready to integrate with the rest of the hull structure or topsides. The seaworthiness of the barge, tug, ship, towing equipment, lashings etc. all come under the scope of the Marine Warranty Survey. If it is a particularly unusual or heavy load then it may be necessary to carry out suitability surveys of the load- out and load-in quay facilities.
It is really impressive how ‘we’ have evolved the production processes for shipbuilding and in doing so built some amazing tools to make those processes easier and more efficient. Namely the floating cranes and goliath cranes. These must be regarded as some of the world’s most impressive engineering achievements, which as tools, are used to make even bigger mega structures.
As marine warranty surveyors, we have the privilege of witnessing massive man- made structures and amazing engineering feats that have gone into overcoming technical challenges. Before any lift, we carefully assess the condition of the cranes to ensure they are fit for purpose. Recently, I had the opportunity to work on two offshore projects where we lifted big topside modules, one at Samsung Shipyard and the other from Hyundai Shipyard, using floating cranes, which were involved in some huge load-ins and lifting of structures weighing around 8,000 and 10,000 tons respectively.
Samsung Floating Crane lifting a Topside Module for integration onto Cloral FLNG.
Each crane hook is rated to 1000 ton SWL. The crane has eight independent hooks.
We often use ‘Big’ Shackles and wire strops for lifting operations. These need to be certified with a Safe Working Load and the lifting engineers need to consider what are acceptable factors of safety for every special lift operation.
Samsung Floating Crane being maneuvered by tugs and anchor handling support vessels, with the suspended module.
One shackle weighs 25 ton
Installing one lifting wire with the 25 ton shackle onto the module lifting point.
One lifting wire secured to the module with 25 ton shackle.
58 | ISSUE 106 | DEC 2023 | THE REPORT
Four-man rigger team needed to position the shackle and insert the shackle pin.
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116 |
Page 117 |
Page 118 |
Page 119 |
Page 120 |
Page 121 |
Page 122 |
Page 123 |
Page 124 |
Page 125 |
Page 126 |
Page 127 |
Page 128 |
Page 129 |
Page 130 |
Page 131 |
Page 132 |
Page 133 |
Page 134 |
Page 135 |
Page 136 |
Page 137 |
Page 138 |
Page 139 |
Page 140 |
Page 141 |
Page 142 |
Page 143 |
Page 144