The I Lift NY crane places a 750,000 pound section of structural steel to connect the Rockland Approach to the Main Span. This work in early February of 2017 was the first connection between the cable-stayed Main Span and any of the pier supported approaches.
Photo courtesy New York State Thruway Authority
To handle the job, Fort Miller hired additional staff and added a 12,000-square-foot facility featuring two overhead cranes. Similar advantages were enjoyed by the subcontractors who assembled the massive girder sections on-shore at the Port of Coeymans facility—a sixteen-acre riverfront site in Albany county. Assemblies with multiple girder—each several hundred feet long, with many weighing more than 700 tons—had a variety of mechanical and electrical components installed before being shipped down for installation, boosting safety and efficiency.
Installation of a precast crossbeam between a pair of main towers
I Lift NY Puts Pieces in Place After months of work to modify and update a variety of systems, including replacement of its rigging cables, Te I Lift NY super crane completed its first lift on April 24, 2015. In an operation requiring more than three hours, it lifted and placed a 600-ton precast pile cap. Tose components link the underlying piles into a support structure for piers and towers above. Numerous pile and pier caps would follow before the bridge would really begin to assume its shape—rendered in structural steel. In June of 2015, the super lifter placed the first
steel girder assembly in a lift totaling up at 1,360 tons including the rigging and lifting frame. Te lifting frame is engineered with hydraulic systems to adjust the load and allow precise placement of this 410-foot-long assembly and 133 others to eventually be incorporated into the project. Placement of steel continued into 2016, and in the early spring, extensive preparation and favorable weather combined to allow the teams to install about 1,400 feet of girder structures in a little more than one week. A major milestone came to pass in the first week of October 2016, when the final girder assembly of the Westbound span was placed—less than a year before it would be handling traffic.
Photo Courtesy New York State Thruway Authority 26 NOVEMBER–DECEMBER 2017 WIRE ROPE EXCHANGE
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84