This page contains a Flash digital edition of a book.
RISK MANAGEMENT RISKS IN OFFSHORE WIND FARM PROJECTS


In the UK Round 2, project owners built medium size offshore wind farms with increasing complexity when the industry had to deal with emerging problems such as grouting specifications, shortage of experienced skill set, issues with long lead items, high vessel costs, key contractors going into liquidation. Some projects experienced considerable cost escalation during the construction phase of projects, not to mention delay in completion dates.


SO WHERE DID THINGS GO WRONG? One of the problems was the weaknesses in contracts – leaving projects exposed to serious risks which were not adequately assessed for consequences in the event of default in contractual obligations.


Another issue was over-confidence among some project team members in their assessment of technical and commercial aspects of their packages, eventually leading to costly design changes during the construction phase, sometimes also


quality failures, unexpected number of drills actually required to install monopile foundations; actual soil conditions resulting in mismatch between budgeted installation activities and actual installation activities; lack of vessel availability; inadequate installation crane capacity; grouted connection issue; late design decisions; lack-of experienced offshore installation man-power availability and interface issues between the project packages.


COMMON AIM


The project teams set out with the common aim of completing their projects as designed on time within budget and without safety and environmental incidents. They prepared project execution plans; selected contractors; assessed technical and commercial risks; focused on best HSE practice; addressed interface issues and utilised their support functions to enable smooth running of the projects. Some of the projects still ended up with cost increases and delays as well as serious safety issues that not only delayed the projects but also caused strain on corporate reputation and project finances.


resulting in delay to the project programme. Some teams chose to rely solely on qualitative risk assessments; this approach did not provide them with quantitative information on the cost and schedule. Hence the impact of risks which was overlooked, was experienced throughout the construction phase of projects.


COMMON PROBLEMS


The offshore wind farm project teams experienced common problems resulting in cost increases which could have been avoided thus making the project financially more viable. Some of those common problems include manufacturing


LESSONS LEARNED


We now have crucial lessons learned from actual project experiences and we can better address the ways in which cost can be saved without compromising quality and schedule throughout offshore wind farm construction in new projects.


Jale Cairney Business Development Director ABS Group Ltd


www.windenergynetwork.co.uk


87


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100