ANOTHER SUCCESSFUL WIND TURBINE CONNECTION AT TAI HEN
g2 Energy were engaged by Belltown Power Limited, to undertake the civil and electrical ‘balance of plant’ works on a single wind turbine in Anglesey, Wales.
This is an EWT 500kW machine, installed under the Government's ‘Feed in Tariff’ scheme, where the generated electricity is being exported back into the national grid.
PROJECT DETAIL AND LIAISON g2 Energy are an independent connection provider (ICP) providing both contestable and balance of plant works for voltages up to 132kV, as an alternative to the local DNO (Distribution Network Operator). For this project, g2 Energy was responsible for the complete design and construction of the wind turbine foundation, both the DNO & client electrical substations and the associated electrical installation works.
g2 Energy also liaised with the DNO, Scottish Power Energy Networks (SPEN) regarding the 11kV electrical grid connection.
CIVIL WORKS UNDERTAKEN INCLUDED… • Civil design and construction of the wind turbine foundation, including cable ducting and reinstatement
• Civil design for the client-side GRP substation
• Design of the access track and crane pad • Earthworks and construction of the access track and crane pad
• Construction of the client-side substation, plus a suitable foundation
• Construction of the SPEN designed brick-built substation
ELECTRICAL WORKS INCLUDED… • Design and installation of the earthing system
• Installation of 800kVa 11/0.690kV transformer
• Electrical design works including single line diagrams
• Supply & installation of an auxiliary low voltage supply at the substation
• Supply and installation, plus terminations and jointing of 11kV cable
• All associated testing CROSSING COUNTRIES
Mabey Bridge, the South Wales based supplier of wind turbine towers, has made the final delivery for the 37MW Clashindarroch wind farm in Scotland ahead of schedule.
The towers are being installed as part of eighteen Senvion MM82 turbines, generating enough clean energy to power over 22,000 homes. The news follows the announcement in May that Mabey Bridge completed the delivery of
fourteen wind turbine towers for Senvion at Goole Fields wind farm in East Riding, Yorkshire.
56
www.windenergynetwork.co.uk
SUCCESSFUL CONNECTIONS g2 Energy have successfully connected 42 single site 500kW wind turbines to the national electricity grid, with a further 43 turbine projects currently in construction.
This contributes to a total of 373MW of renewable energy connected to the grid by g2 to date, with a further 703MW due to be connected by mid 2015.
g2 Energy
FINAL TURBINE TOWERS LEAVE MABEY BRIDGE FOR CLASHINDARROCH AHEAD OF SCHEDULE
Planning permission for the Clashindarroch wind farm was granted in December 2010 by Aberdeenshire Council, with preliminary construction work beginning in June 2013. The wind farm is expected to be completed by March 2015.
DELIVERING AHEAD OF SCHEDULE Mark Coia, Managing Director of Mabey Bridge Energy & Marine commented: “We are delighted to deliver our turbine towers to Clashindarroch ahead of schedule to help ensure the wind farm is operational as soon as possible. As a British manufacturer we have worked closely with Vattenfall and Senvion to increase UK content in the wind farm and look forward to working in partnership on similar projects well into the future.”
KEY MODEL
Raymond Gilfedder, Managing Director of Senvion UK added: "The MM82 machine is a key model for Senvion with over 300 installed in the UK alone and this positive progress for Clashindarroch wind farm clearly demonstrates the ongoing successful relationship between Senvion and Mabey Bridge.”
Mabey Bridge Energy and Marine
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100