search.noResults

search.searching

dataCollection.invalidEmail
note.createNoteMessage

search.noResults

search.searching

orderForm.title

orderForm.productCode
orderForm.description
orderForm.quantity
orderForm.itemPrice
orderForm.price
orderForm.totalPrice
orderForm.deliveryDetails.billingAddress
orderForm.deliveryDetails.deliveryAddress
orderForm.noItems
DATA CENTRE COOLING


centre’s overall efficiency and EER ratings, reduce emissions and offer an attractive ROI. Legacy systems present their own unique challenges and require innovative solutions. The criticality of the site, logistical issues, redundancy and fast re-start requirements often require a customised approach which not all manufacturers can provide.


The solution comprised of four equally sized 1.1mW chillers using the latest multi-turbocor oil free compressor technology, and an off load and duty assist configuration would ensure the best possible energy savings. The chillers were rigorously performance tested before being shipped to site and re- tested once in situ.


The tests results were positive and met the predicted EER ratings.


Each chiller achieved on average between 6.68 and 7.43 EER under normal use and savings calculated showed a £67K saving per annum on a single chiller and £200K


per annum collectively during sequenced deployment at contracted cooling load, compared to the previous chillers. Based on these results, it is anticipated that customer will save up to £2million over the next 10 years.


A phased approach was adopted for the installation with one chiller installed at a time. The project presented a number of challenges.


Working in a ‘live’ data centre meant that installation and commissioning had to be carried out sensitively so that the client’s customers were not impacted by the replacement. The existing chillers were sited in a basement plantroom, residing in the vaults.


De-commissioning and reducing the


legacy units into small sections for removal was straightforward, but installing the replacement units required a creative approach. Aermec engineers ensured that


not only were the customers’ requirements addressed, but designs were engineered to enable easy access.


To achieve a smooth replacement right


from the outset engineers designed a bespoke chiller frame assembly; arranging the evaporator and condenser shells as a single component and to dimensions that enabled its transfer through the plantroom doors and below the installation pipework, leaving a 5mm tolerance. The new sections and frame were then passed through a space limited to a headroom of only 1435mm. The chillers were transported in component form and re-built on site.


The project took place over a 10-month period and to facilitate the replacement, cryogenics were used to freeze the pipework. The project was challenging but the


customer was able to realise a short term- ROI and a significant environmental benefit, resulting in a very satisfied client.


Swegonair WISE


Demand Contr olled Ventilation with in telligence and simplicity built-in


WISE b egins with our soſtware at the design stage to help identif y the right ven tilation solution for your project. Wireless commissioning of WISE is effortless and SuperWISE provides a real-time system overview


to k eep your project smooth from start to finish and beyond.


Find out mor e about WISE wise.swegon.com


43


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64