This page contains a Flash digital edition of a book.
294. It is likely that the locations at which cable burial would not be possible and cable protection would be required would coincide for all three projects creating a concentration of cable protection in one area.


295. Furthermore, the 12 cables would cross three export cables from Greater Gabbard Offshore Windfarm and up to three cables fromGalloper OffshoreWindfarm. This would result in up to 72 cables crossings which may all be located in an area of approximately 13.76km² Figure 10.13.


296. Depending on the nature of how these cables would be crossed and what materials would be used, the magnitude of this cumulative impact could be medium with so many crossings in a concentrated area although not significant in the wider context. As discussed previously the sensitivity of the habitats and species present within the offshore cable corridor is considered to be low and species and habitats would be expected to recover rapidly after disturbance even if construction periods of windfarms were to overlap. Therefore the impact is ofminor adverse significance is predicted.


10.7.2.2 Impact 2: increased suspended sediment leading to smothering 297. The marine aggregate extraction licence Area 430 is located approximately 925m north of the northern boundary of the offshore cable corridor3. Sediment plumes from dredging vessels can extend on the tide for up to 2.5km from the vessel. If aggregate dredging takes place in Area 430 at the same time as the offshore cable corridor installation work, there would be potential for cumulative impacts from elevated turbidity and smothering on the benthos within the footprint of the two sediment plumes. However, as a result of the limited duration and low probability of this scenario occurring, combined with the low sensitivity of the habitats present to increased suspended sediment concentrations and smothering (as previously discussed, Construction Impact 3 and Operation Impact 3) the cumulative impacts are considered to be at worst minor adverse significance.


10.7.2.3 Impact 3: Colonisation of Introduced Substrate 298. As previously discussed in section 10.7.2.1 there could be up to 72 cable crossings between the East Anglia cables from projects ONE, THREE and FOUR and the Greater Gabbard Offshore Wind Farm and Galloper Wind Farm export cables. These cable crossings would require cable protection at each crossing point. The nature of the cable protection is likely to be concrete mattresses no more than 1m high. These would represent the introduction of a hard substrate in an otherwise sediment habitat and would therefore be colonised by marine flora and fauna.


3 Note that Licence Application and Prospecting Area 496 is also located approximately 2.5km to the north of the offshore cable corridor however this area is no longer being taken forward for extraction.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 1 Introduction Page 84


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104