Consultee Evidence Plan


Cefas and Natural England


September 2013


Agree that the time for specific Sabellaria surveys would be the preconstruction stage and would not be required for the EIA. With any avoidance achieved within the project redline boundary through micrositing.


Cefas and Natural England


Cefas and Natural England


September 2013


September 2013


Agreement that sufficient benthic ecology survey data has been collected for EA THREE.


Agreement that the list of impacts proposed by EATL in the Evidence Plan method statement is comprehensive (Appendix 10.1).


EATL have made a commitment to conduct preconstruction surveys (section 10.3.3).


Survey data are presented in section 10.5 and in Appendix 10. 2, 10.3 and 10.4.


Sections 10.6 to 10.8 assess all impacts agreed within the Evidence plan process as well as others that were identified outwith the Evidence plan.


Cefas and Natural England


September 2013


Agreement of the proposed methodology for each impact (Appendix 10.1).


Each of the identified impacts (section 10.6) have been assessed using the methods agreed within the evidence plan (Appendix 10.1).


Cefas and Natural England


Cefas and Natural England


September 2013


Agreement that the sensitivity and magnitude definitions are appropriate (Appendix 10.1).


September 2013


Agreement that no site specific modelling of sediment dispersal will be required for assessing benthic ecology (Appendix 10.1).


Impacts have been assessed using the methods agreed in the Evidence plan. (section 10.4)


The assessment for impacts associated with sediment dispersal has applied a more qualitative approach, using the modelling carried for East Anglia ONE as a proxy.


Date /Document


Comment


Response / where addressed in the PEIR


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 10 Benthic Ecology Page 5


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104