This page contains a Flash digital edition of a book.
 Underwater noise and vibration; and  Colonisation of foundations and cable protection.


289. These impacts would mostly be temporary, small scale and localised. Given the distances to other activities in the region (e.g. other offshore windfarms and aggregate extraction) and the highly localised nature of the impacts above there is no pathway for interaction between impacts cumulatively. Whilst it is recognised that across the East Anglia Zone and wider southern North Sea there would be additive impacts, the overall combined magnitude of these would be negligible relative to the scale of the habitats affected. In addition, given the ubiquity and low ecological sensitivity of habitats across the southern North Sea (and indeed across areas deemed suitable for development) sensitivity is also likely to be low or negligible at a cumulative scale.


290. In the case of physical disturbance and smothering during construction there is only potential for such additive impacts if project construction schedules overlap (for example the preliminary stages of construction of East Anglia FOUR may overlap with the final stages of construction of East Anglia THREE). Again although there may be an additive impact these are likely to be of negligible magnitude. In cases where sensitive habitats are present (e.g. Annex I reef), effects would be avoided where possible by micro-siting and design in those projects (as has been committed to for the proposed East Anglia THREE project), therefore there would be negligible or no impacts to these features.


291. Therefore, given that the impacts assessed for the proposed East Anglia THREE project (i.e. project level impacts) are considered negligible or would be avoided by design it is considered that at a cumulative (i.e. additive) level, impacts upon the benthos would be negligible.


10.7.2 Offshore Cable Corridor 292. There is potential for cumulative impacts to occur through the interactions between the proposed East Anglia THREE project export cable and export cables from other windfarms as well as interactions with aggregate extraction sites.


10.7.2.1 Impact 1: Physical Disturbance and Habitat Loss 293. There is a potential for cumulative impacts to occur within the offshore cable corridor where the export cables of many different windfarms would be in close proximity to each other. Up to 12 cables from the proposed East Anglia ONE, East Anglia THREE and East Anglia FOUR projects would be installed roughly parallel to each other and share the same offshore cable corridor to the landfall.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 1 Introduction Page 83


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104