This page contains a Flash digital edition of a book.
that the East Anglia THREE site would require up to 730 visits by a jack-up vessel per year.


10.6.2.2.1 East Anglia THREE site 239. It is very difficult to predict the level and extent of maintenance activities that may occur during operation.


240. As previously described in Construction Impact 1 (section 10.6.1.1), jack-up barge feet would penetrate the sea bed disturbing the habitat and affecting the organisms within the footprint. It has been estimated that the maximum area of disturbance would be 0.87km2 per year (Table 10.2) could be caused by Jack-up vessels. The duration of the effect would be temporary and whilst individuals directly within the footprint would not recover, the numbers concerned would be low and there would be no long lasting effects on the wider habitat. Taking this into account, the magnitude of effect would be low.


241. Maintenance work may also be required on cables installed within the East Anglia THREE site. However, it is expected that if the cables are buried to their target depth of between 0.5 and 5m there would be minimal amounts of maintenance required. Therefore, the magnitude of physical disturbance during operation is predicated to be negligible.


242. The receptors to physical disturbance during operation would be the same receptors as those identified in section 10.6.1.1. (Construction Impact 1). These receptors were identified as being of low sensitivity (section 10.6.1), therefore given the negligible magnitude of effect the impact of physical disturbance during operation is predicted to be of negligible significance.


10.6.2.2.2Offshore Cable Corridor 243. The export cables could also require maintenance that may result in physical disturbance. As with the windfarm cables, it is expected that, if the export cables are buried to their target depth of between 0.5 and 5m, there would be minimal amounts of maintenance required and any repair operations would involve temporary and infrequent activity. Therefore, the magnitude of the impact is likely to be negligible.


244. As previously discussed, the habitats within the offshore cable corridor are typical of the East Anglia Zone and the southern North Sea.


245. The sensitivity of the species and habitats within the offshore cable corridor to physical disturbance is discussed in section 10.6.1 (Construction Impact 1) with the conclusion being that sensitivities were either low or medium.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 1 Introduction Page 75


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104