This page contains a Flash digital edition of a book.
Business profile


were scraped from the cutting face and the top of the central spine using ultra- long reach excavators. The work reduced the angle of the face itself from the point where the valley gravel’s layer sits above the chalk, reducing the amount of material that sits above it and minimising the possibility of any slip failure. The finished face was also nailed and meshed to prevent any falls. O’Donovan said the scheme was ‘complicated’ but the team completed a project that the Victorians would admire.


the southern end of a 650-metre section of work is also contributing.’


A layer of gravels, stones and boulders


sits on top of the chalk strata which makes up this section of the North Downs. At the Hooley Cutting, the layer of gravel thickens, becoming less stable where the Victorian engineers cut through it and prone to landslips which have caused derailments. ‘It’s not so much the inclination of the


chalk strata that affects the slope stability but the layer of dry valley gravel above it. Dry valley gravel is just a geological term for the material - it’s anything but dry and can slip into the cutting,’ said O’Donovan, which is exactly why the stabilisation scheme has been carried out on behalf of client Network Rail.


Work at Hooley Cutting The BAM Ritchies team began work at the Hooley Cutting site over Christmas 2011 and stabilisation work took place in late 2012 into 2013. The cutting was broken down into four separate sections and the team installed the three stabilisation solutions. The four sections were: on the western


slope from the tunnel portal through to the first row of houses that teeter at the top of the cutting; then the Esso houses section a little further down the cutting; the new beam and grillage section and lastly, the central spine. In the two ‘houses’ sections the dry


valley gravels were stabilised through the use of 100mm diameter soil nails installed at depths of up to 14m at nominal 1.5m centres. The highest line of nails is encapsulated in a 430-metre crest beam installed along most of the 620m length of the cutting forming part of the new access and inspection walkway. Drilling and grouting for the 6,200 soil nails was carried out by three Rippamonte


Page 118 October 2013


hydraulic slope rigs, specially built for the BAM Ritchies team. ‘Despite its name, the dry valley gravel


material that we drilled into was neither dry nor particularly granular. It’s a real mix with the bore incapable of staying open after drilling. That’s why we grouted them up immediately,’ explained O’Donovan. Toward the northern end of the


cutting the team installed 21 new concrete columns along the face. These were crossed with the crest beam and a further beam at the lowest edge of the dry valley gravel with an intermediate concrete beam placed between the two. Due to access issues and the slope’s steep gradient, the reinforced concrete columns were placed with spray applied concrete techniques Across the railway line and in the


central spin, major earthworks were carried out to reprofile the dry valley gravel layer. Around 14,000cu metres of this layer


Crossrail In London, BAM Ritchies is heavily involved in the Crossrail project with compensation grouting works for the BAM Nuttall/Ferrovial and Kier JV’s contract, C300 - the western running tunnels currently progressing east from Royal Oak, under London’s West End and on to Farringdon just outside the City. This work, along the Crossrail route, is set to limit settlement caused by the tunnelling operations. Recently, the drilling and installation of approximately 40,000 metres of tube-a-manchettes necessary for the grout injection was completed and grout injection continues as the tunnels advance. Levels of potential settlement vary according to the different tunnel and excavation methods used. BAM Ritchies engineering manager


Owen Francis was part of the team ensuring that settlement is within agreed guidelines. ‘The maps of the route highlight every heritage structure or listed building along its length and the degrees of risk of settlement associated with the work. Obviously the project involves tunnelling beneath London, so there are plenty of issues,’ said Francis. Work is on schedule and grouting is expected to continue well into next year.





Visit www.bamritchies.co.uk Tel 01236 467000


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140