SPECIAL WORKS


Clearing tarmac and concrete using a Picote Miller


C.J. Kelly International Ltd recently assisted in a challenging pipe cleaning project being undertaken by specialistDrainage contractor FastflowDrains.WorkingwithDerek Sewell of Fastflowthe project required the removal of tarmac and concrete deposits froma pipeline serving theWinchester Court residence in Vicarage Gate LondonW8, UK.


The pipeline in question comprised a cast iron drainwhich runs directly under the property in solid ground and concrete negating any potential for traditional open cut replacement of the pipeline, so a trenchless solution had to be found. The build-up of tarmac and concretematerials in the drain,whichwas highlighted by a CCTV survey,were causing damp problems in the basement flat of the property.


Assessing the problemand havingworkedwith CJ Kelly International on previous occasions, Derek sought advice on themost effective options for removing the offendingmaterials. Having heard recommendations fromother drainage contractors Derek asked about the potential use of a Picote SuperMidimillermachinewith the correct cleaning attachments.


Consultingwith CJ Kelly proved highly effectivewhen John Kelly recommended the SuperMidiwith a selection of Tiger cleaning tools.


Renting themachine to complete theworks the Fastflowteamset up the SuperMidi on 7 December 2020 at 08.30, thiswas in order to start the cleaning operations promptly at 09.00. The later startwas out of consideration to the residents. The cleaning operationwas completed by 14.30 in less than one normalworking shift and themachinewas demobilised and removed fromsite.


Fast Flowused the Picote SuperMidimachine for cutting out the tarmac and concrete fromthe cast iron drain utilising the Picote cutting headswith a Tiger bore drill head, a 100mmdiameter Tiger Drill chain, a 75mmdiameter Tiger twister concrete/liner removal tool, a leader cable, hub and grinding panels and a Flexian 3,000 psi@16 gpmhigh pressurewater jettingmachine. The operationwasmonitored using an A&MIndustrial CCTV Camera system.


The Picote SuperMidi set up for the cleaning operation.


The Picote SuperMidi removed the tarmac and concrete in just 3 passes through the pipeline, using the Tiger twister concrete removal tool. The contractor then ran themachinewith the tiger drill chain and leader cable hub and grinding panels to clean up any remaining deposits. The drainwas then finally cleaned utilising the high pressure water jetting systembefore completing a final CCTV Survey.


The pipeline before cleaning commenced holding water behind the tarmac and concrete blockage.


42 | February 2021 | www.draintraderltd.com


The pipeline after cleaning completed.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80