CABLE INSTALLATION ADAPT OR GO HOME


In combining all of the above: leveraging a good relationship with our client, retaining the same team throughout where possible, application of state of the art IT solutions between vessel and onshore team to ensure swift adoption of incremental changes to procedures, implementing trialling lessons early on and of course utilising the class leading Siem Duo spread, meant that we were able to effectively and efficiently deal with unforeseen challenges which would otherwise have led to significant delays and cost increases on the project. One such example was the non-


foreseen design issues on messenger wire installations. On Veja Mate these wires were intended to be pre-installed onshore in the foundations, in order to be used to pull the subsea cable through the monopile entry-hole up inside the monopile to cable termination. Although a very small part of the overall procurement within cable installation, they are critical to ensure cables can be pulled in. Therefore technical interface issues between the monopile entry hole cover (connection point between messenger wire and subsea cable) and the hydro- sound damper required to minimise the noise emanating from the foundation installation for environmental reasons, revealed a significant project risk to Veja Mate. We quickly developed and adopted an offshore messenger wire installation solution using the WROV in combination with minor foundation design adaptions. This was quickly and efficiently developed, agreed with the client and then rolled out across the foundations without impacting the project schedule or experiencing any quality incidents.


EXPERIENCE The Team


…BUT SO IS SOPHISTICATED PROJECT PLANNING


Siem Offshore Contractors has always insisted on undertaking cable installation mock-ups ahead of fully fledged offshore operations and Veja Mate was no different. Validation of offshore processes and design interfaces can be performed when you don’t have ships in field, saving time and significant money. Identification of potential issues in an early project phase reduces the risk of


cost of poor quality for all related project stakeholders significantly. Limiting learning curves to early phases also benefitted offshore personnel management. Maintaining experienced personnel from former projects and transferring project engineering personnel from the onshore teams on the Siem Moxie were measures taken, as well as training our teams on the project design and procedures well before offshore work commenced, thereby expediting operations.


Siem Offshore Contractors has completed cable installation jobs on five offshore windfarms in the UK and Germany since 2011 and has commenced work on the Beatrice, Hornsea One and Trianel Borkum II array cable packages. We hope to be able to share more insights in future editions!


Alex Gauntt & Sebastian Zaitz Siem


SCAN/CLICK


MORE INFO


www.windenergynetwork.co.uk


69


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76