CASE STUDIES


Chiller hire prevents server room shutdown


T


emporary short-term hire of two compact 100kW chillers from Andrews Chiller Hire provided essential support to maintain optimum temperature within the data centre of one of Britain’s leading communications companies whist their in-house air conditioning was taken off -line. This prompt action by Andrews provided protection to critical equipment in the server room, preventing disruption to their business and customer services. Data centres require effi cient air conditioning to ensure the smooth running of their servers. Heat can build up for many reasons, including a lack of air fl ow, heat spots caused by server positioning, the existing air conditioner’s ability to deal with the heat load, and ineffi cient air conditioning solutions.


Some businesses will have a secondary air conditioning supply in place to avoid the dreaded downtime experienced when servers shut down due to the rising temperature. This is especially true for commercial data centres, which are processing millions of pounds’ worth of


64 November 2017


transactions each day from across the globe. Should an organisation’s backup fail, the availability of emergency air conditioning is non-negotiable, especially when downtime will usually result in a great deal of lost revenue. With emergency maintenance work required on the existing cooling system at the communications centre, it meant all existing air conditioning in the data centre would be switched off . To prevent equipment failure through overheating and subsequent business interruption, a temporary solution needed to be sourced urgently.


A technician from one of Andrews Sykes’ local depots visited the premises to conduct a site survey. Assessing the situation, it was determined that there was a need for 200kW of cooling duty on site.


Due to a restriction in height and an inadequate on-site power supply, the technician decided that the best solution would be to supply two 100kW temporary chillers and a 200kW air handler.


Once the temporary chillers had been commissioned for this major communications organisation, they worked perfectly, distributing an optimal level of cooling throughout the data centre and averting potential plant closure. Andrews Chiller Hire, a specialist in providing tailored air conditioning solutions at short notice, operates with one of the largest chiller hire fl eets with capacities ranging from 30kW units to multi megawatt packages. It also has over 20 depots strategically positioned throughout the UK, which ensures that equipment can be despatched and on-site as quickly as possible. These factors plus expert knowledge often make Andrews Sykes the preferred responder in an emergency.


www.acr-news.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76