NEWS
A quiet payment revolution ta
akes
L
ast year’s collapse of Welsh- based company Dawnus Construction has hastened
progress towards protecting SME payments in Welsh construction. I n December 2017 Mark Drakeford, then Cabinet Minister for Finance, launched a new project bank account policy “to support ethical business practices in government funded construction.”
All government funded projects in Wales above a £2 million threshold are required to have a project bank account (PBA). A PBA enables all fi rms in the supply chain to be paid from one “pot” without payments having to cascade through the diff erent layers of the supply chain. The monies are ring-fenced so that if there is an insolvency upstream small fi rms in the supply chain don’t lose out; in the Dawnus collapse almost £40 million was left owing to Dawnus’s supply chain.
At a recent event hosted by SEWSCAP, the largest value
framework in Wales, councils and contractors came together to determine how best to implement the policy on PBAs. Those who had already used PBAs indicated that they helped to ensure that payments to SMEs in the supply chain were discharged well within 30 days as well as being made secure.
Speaking on behalf of SEWSCAP
Kevin Shackson, who chaired the e vent, said he was delighted with the progress being made on using PBAs: “It’s such a commonsensical thing to do. Most of construction in Wales is actually delivered by small fi rms. They deserve proper payment protection since they provide a range of community benefits including local jobs and training.”
Speaking at the event Luke
Owen, managing quantity surveyor at Morgan Sindall’s Cardiff ffi said:? “As a large tier 1 contractor we fully support PBAs. Contrary to various adverse reports the costs and administration involved in setting up and operating them is minimal. On the positive side we fi nd that they help to improve the performance of our supply chain. We are grateful to SEWSCAP for bringing together public sector authorities, contractors, consultants and sub-contractors to work collaboratively to implement PBAs in South East Wales.” Cat Griffi
offi c e ffi th-Williams, nationa l
executive offi cer for the Specialist Engineering Contractors’ (SEC) Group Wales (representing engineering SMEs in Welsh construction) added: “Feedback from firms which have experienced PBAs has been amazing. They don’t have to wait months to get paid and they can commit to their work in the knowledge that their monies are secure.”
Ou
Our strength is our fast response
Quality engineering pr oducts for NH3, CO2 and other refrigerants from leading European manufacturers
r
• Open Refrigerant P umps • Hermetic Pumps NH3/C O2 • Pressure Vessel s • Sur ge Drums
• Liquid Receiv ers • Economisers
• Oil Recovery S ystems
• Chilled Water/Brine Chiller s • Ammonia Spr ay Chillers • High Pressur e Floats • Stop Valves NH3/CO 2 • Ball Valve s
• Electric and Pneumatic Ball ValvValves • Flap Indicators • Oil Separ ators
• Circular Welded Plate Heat Ex changers
• Shell and T ube Condensers • DX Chillers •
Heat Ex changers Br azed Plate
• Shell and Tube Heat Exchangers • Capillary Hose
www.acr-news.com
7
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76