Phasing and timing of deliveries will be adhered to in order to ensure that working hours and restrictions upon delivery times are honoured to avoid unnecessary congestion, taking into account other committed developments and seasonal variation


Timings and notice periods for abnormal load deliveries will be agreed with SCC in reasonable time. Post-construction surveys and follow up reinstatement will be undertaken to ensure that any damage is remediated


The need for additional traffic measures at particular pinchpoints where HGVs cannot pass in opposing directions – such as the B1079


Consideration to the size of vehicles appropriate to each section of the access routes.


19


Details of compliance and enforcement measures regarding construction logistics management would be agreed with the relevant highways authority prior to commencement of works. However, the following broad measures would apply:


20


The Main Works Contractor would be required to comply with the HGV routes as assessed and agreed with the relevant highway authority through the final Traffic Management Plan


21 A system for ensuring compliance with the defined HGV routes could involve a vehicle registration system and log at Construction Consolidation Sites (CCSs) and an HGV stickering system, with an advertised public complaints procedure


22 A complaints procedure would be publicised and complaints would be directed to EAOL. Details of complaints would be reported to the relevant Local Planning Authority and relevant highways authority on a regular basis, through a regular liaison group


23 Any sanctions for contraventions of the agreed construction logistics would be agreed prior to commencement of works with the relevant highway authority and set out in the final Traffic Management Plan.


1.7 Road Crossings 24


The locations of and preferred method of crossing each highway, footpath, public right of way or bridleway by the proposed cable route has been previously identified in the DCO in Schedule C, Part 3, 9-(1)-(3). Any changes to this proposed schedule would be agreed with the relevant Local Authority.


Outline Traffic Management Plan – Version 3 Page 10


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32