This page contains a Flash digital edition of a book.
21.6.2.1 Impact 1: Impact to Groundwater and Surface Water


21.6.2.1.1 Landfall and onshore cable route 92.


Routine maintenance works would be required during the operational phase; however, this access would be via jointing pits or kiosks, and any excavation will be limited to the area around those, and therefore would result in minimal disturbance. In addition jointing pits will be located at least 10m from watercourses and at a maximum depth of 2.5m. Therefore it is believed unlikely that there is any pathway for impact to groundwater levels and quality and surface water flows and quality from routine maintenance.


93.


In the event of a cable failure, it may be necessary to re-excavate the cable trench and replace / repair the faulty cable along limited stretches. At major water crossings, the cables installed via HDD and would be within ducts. Therefore if cables need to be removed at these points there would be no interaction with the watercourse itself. Works would be based around jointing pits which would be located 10m away from any watercourses. Therefore for major water crossings it is considered that there is no pathway for impact during operation. This is also the case for minor water crossings under Scenario 1.


115. For smaller water crossings where open trenching takes place under Scenario 2, if repair works are required, the mitigation measures outlined for the construction phase activities in section 21.6.1 would be adhered to, in order to reduce or minimise any potential impacts to an acceptable level. It is considered that the impact significance of this would not exceed minor adverse at the location affected. Mitigation would also be employed to ensure spills and leaks are avoided or contained as described in Table 21.14.


21.6.2.1.2Converter station 116. There are no watercourses at the converter station location and therefore there would be no direct impacts on surface waters. Mitigation would also be employed to ensure spills and leaks are avoided or contained as described in Table 21.3 and Table 21.14. In addition note that the design of the converter station compound will incorporate a sustainable drainage system (SuDS) and runoff will be managed to maintain greenfield runoff rates. In addition, there will be sufficient site attenuation for rainfall up to 1 in 100 year probability events, plus a 30% allowance for climate change.


21.6.3 Potential impacts during Decommissioning 117. This section describes the potential impacts of the decommissioning of the onshore electrical transmission works with regards to impacts on water resources and flood


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 21 Water Resource and Flood Risk Page 41


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58