 Access via existing roads and tracks and therefore no haul road is required except for where joints are placed in remote areas. A maximum of 16.1km of 5.5m width haul road is required. Temporary track matting may be required if ground conditions are very poor.


 Construction Consolidation Sites – nine in total mostly on brownfield sites up to 10ha in total.


 Reinstatement of land. 15.


The onshore cable route is approximately 75m in width except at the HDD locations where spacing of ducts will be wider. Within the onshore cable route a working width of 55m will be required. Within this working width there will be space for any haul road, temporary laydown areas, jointing pits and temporary spoil storage.


16. Note that the haul road requirement under this scenario is currently being reviewed. In the original design iteration for this option it was assumed that all access to the onshore cable route would be made via those access points identified for East Anglia ONE. This would in places require the removal of hedgerow and reinstatement of haul road to access isolated locations for jointing pits (i.e. those locations which are far removed from field boundaries adjoining roads).


17.


It is desirable to reduce the requirement for haul road for two reasons. Firstly under Scenario 1 the bulk of the materials delivered to and taken off site will be for the creation of the haul road itself. Any reduction in haul road requirement would reduce overall material volumes and therefore vehicle movements. Secondly, if existing tracks could be upgraded to access remote jointing pit locations this would reduce disruption to arable fields (and hedgerows and other sensitive habitats) and provide an upgrade to the local infrastructure.


18.


Use of existing tracks would be subject to consultation with landowners, therefore the red line boundary displayed on the figures for this PEIR show these areas within the boundary in order to prompt consultation on the possible use of new access routes not previously consulted on for East Anglia ONE.


19.


For Scenario 2 it is assumed that the whole of the onshore cable route would consist of open cut trenches, except at the Horizontal Directional Drilling (HDD) locations shown in Figure 21.4. There would be a worse case maximum of 48 jointing pits under Scenario 2.


20.


The worst case associated with watercourse crossings is the use of a dam and over- pump technique, as described in Chapter 5 Description of Development.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 21 Water Resource and Flood Risk Page 7


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58