This page contains a Flash digital edition of a book.
excavation of the numerous on-site water features. The total earth movement quantities have been in excess of 750,000 cubic metres.


We negotiated the required space for the golf course (about 75 hectares including a central lake of about 5 hectares) (45% of the total site area) with RRA to create a “core” golf course, with hotels and residential areas located on the periphery. It was an interesting period of the design process. We produced three or four alternative golf course route plans which were discussed, modified and, finally, we came up with a solution that worked for RRA in design terms, and for MEDZ in relation to the potential sales value of the residential areas.


We took into account the design of the residential areas (more than 1000 properties) and hotels aiming, as far as possible, to maximise their viewing potential (therefore maximising potential revenues), and also to design a course that would not create a safety problem for non-golfers.


In addition, we took into consideration the use of the peripheral areas for circulation - maintaining the main pedestrian access alongside the river and allowing for strong connections between the five on-site hotels via buggy tracks.


We were not asked to compromise the design of the golf course at all by RRA (who had never been involved in the design of a golf resort before, but had masterplanned a number of Moroccan and French cities and towns), or by MEDZ. The golf course was recognised as being the “heart” of the development from the outset and they respected our opinions as golf course architects. Admittedly, it has been a learning process for all members of the design team.


The masterplan was agreed by the authorities (Esquisse) in Autumn 2006 and detailed design work was undertaken over the winter of 2006/7. Permits were granted for the development in Summer/Autumn 2007 and construction work began in November 2007. MEDZ own one other golf course, Royal Golf de Fes, which was designed by American Golf Course Architect, Cabell Robinson, and built in the 1990s. However, they hadn’t built a golf course before, so they asked our advice and we recommended that they employ a specialist project management team, using local, Moroccan companies for all the main works: clearance, earthworks, drainage, irrigation and finishing works.


58


Czech Republic. We knew how they worked and that we could trust them to do another good job for us and our client. The project management team comprises just two people (headed by Chris Johnson with full-time, on-site management by Tom Sedlmeier). Tom learnt French within a few weeks of starting work and quickly integrated into the Arabic lifestyle. Chris and I have been making site visits at regular stages through the construction period to ensure that work gets inspected and approved, however, Tom remains our “eyes and ears” on site.


CJ Management were also responsible for providing a specialist shaper - Chris had a host of good shapers who could do the work in Morocco. However, none were available at the time (Chris was also working on other projects in Egypt and Eastern Europe). We both knew of a shaper from Texas, USA - Lawrence White - who had been working on a project in Bulgaria and his work there had come to an end, so it fitted in nicely. Lawrence started work at Royal Oued Fes in November 2008.


It seems like a long time from commencement of construction work in


concrete pipe) by the engineers, which is not scheduled to be completed until August 2009. Plus, we still have high voltage power cables crossing the site (there is a pylon in the middle of the proposed clubhouse location), which will be removed by July/August 2009 and replaced with a new line of high-power cables on the southern site boundary, running parallel with the railway line. As soon as these are removed the earthworks and shaping work can begin


Our project management team (CJ Management, based in Munich, Germany) had worked with us previously in 2005 at Kaskada Golf Resort in Brno,


November 2007 to starting shaping works in November 2008, however, we had a number of “teething problems” to overcome. These were mainly associated with working on a golf project with local contractors who had never worked on such a project before. There were other issues: heavy rains over winter 2007 and again in winter 2008 caused several month’s delay. In fact, the lakes had only just been excavated to final depth (about 5-7 metres deep) when the rains started in Autumn/Winter 2007/2008: recorded as the wettest winter in Morocco in 50 years!


The lakes remain full with water (May 2009), which is a big problem in that we cannot line them with butyl lining material until they are pumped dry. However, they will provide an excellent water source for the irrigation system when it comes to the seeding works (which are planned for July-November 2009).


Likely seed mixes are:


• Greens: Tee-one (T-1) Bentgrass • Tees/fairways: Riviera Bermudagrass • Roughs: Sheeps/Hard Fescue


Added to the water problem, there remains 350 metres of drainage outlet (sewer) pipe (which will be used for all facilities on site) to be installed (7 metres deep tunnel 1.5 metres diameter


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140
Produced with Yudu - www.yudu.com