“I am in a very fortunate position of having excellent backing from the senior management at the club”
agents and liquid aeration products.
Unfortunately, there was little we could do to resolve some of the other issues, such as the surface levels and root- zone depth; we have the Desso system which would have to be replaced if these were to be overcome. Up to the end of last year the pitch seemed to be responding to some of the measures we had put in place but, as soon as we reached prolonged spells of wet weather, the surface began to deteriorate. We continued to carry out the maintenance procedures we had decided upon, and even increased our aeration programme. At the start of February we decided to try another option, which was to Dry-Ject the surface. This was an operation we knew had been carried out successfully at Southampton, Wolves and Blackburn. It involves using a pedestrian machine to drill kiln dried sand or other products directly into the soil profile. We applied 17 tonnes of kiln dried sand to the profile to increase the percolation rates. Unfortunately, we had limited success with the operation due to the poor condition of our root-zone and, in hindsight, we had perhaps tried this option too late in the season as a cure rather than prevention in the first instance.
Having tried various options to improve the surface with limited success, and also combined with the problems of surface levels and root-zone depths, I consulted my Stadium Manager, Ray Booth, and informed him that I felt the only course of action would be a full reconstruction of the pitch to enable us to present a suitable surface for the up-coming season. After discussion, this was agreed in principle with the Chief Executive, as we all felt that this would be the ideal time to carry out such an operation as the team had ensured Premiership survival for this season.
I am in a very fortunate position of having excellent
16
backing from the Senior Management at the club, especially the Stadium Manager whose unenviable task it is to present my requests to the Board. Our next task was to decide whether we needed to replace the entire profile of the pitch, including drainage and under soil heating, or just to replace the root-zone and Desso. After investigation of the drainage system using cameras, it was decided that the drainage was corrupted and that we could not take the risk of building a new profile on top of this system. Once we had decided on our course of action we contacted Hewitt Sportsturf, not only because they hold the licence for Desso, but because I feel they are the best in the country at this type of operation having recently completed Wembley and the Emirates Stadium. We met with John Hewitt and, after a series of discussions, agreed that the best way forward was to return the pitch and track to their original levels when the stadium was first constructed. This meant we could leave the existing drainage in place, making it defunct, as the new drainage layer would be above this level. It was also decided that we would engineer the drainage to steeper gradients to counteract any future subsidence. We would also install submersible pump chambers so that drainage would not have to rely on being gravity fed, but could be pumped from the system. It was also agreed to put in upgraded pipework that would allow us to attach mobile Sub-air units in the future, to enable us to circulate air through the drainage system and into the profile.
Because of the relatively short time frame we had to do this work, we planned for the operation to be carried out so that one side of the pitch would be completed before the other; the Desso machines could make a start whilst the other side was
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108