This page contains a Flash digital edition of a book.
© Ian Simpson Architects LONDON UNDERGROUND


Ambitious aims for £1bn Northern Line Extension


Graeme Shaw, head of Northern Line Extension at London Underground, gives an overview of the project and its ambitious aims.


W


ork on the Northern Line Extension (NLE) could be up and running by autumn this year if Transport for London (TfL) gets the nod from the Department for Transport.


If not, it is more likely that the programme, which will deliver two new stations at Battersea Power Station and Elms Park, extending the Charing Cross branch from Kennington, will begin in January 2015.


Speaking at Infrarail, Graeme Shaw, head of Northern Line Extension for London Underground, said the team is in a “limbo period” as it waits for the decision on its Transport and Works Act Order (TWAO) application.


borrowing will come from the private sector through a levy on the area’s development sites and through future growth in business rates revenue.


So far, more than three years of detailed planning and design work have already been completed and the scheme has received widespread backing during its fi rst and second round public consultations. It is now estimated that the NLE will cost £998.9m based on completion by the end of 2019.


Project challenges


Public consultations highlighted the preferred route for the extension, and the TWAO application report is now with the secretary of state for consideration.


Innovative funding


It was confi rmed in the Chancellor’s 2012 autumn statement that up to £1bn of borrowing from the Public Works Loan Board would be available to the Greater London Authority (GLA) to fi nance the construction of the NLE.


In a fi rst for an infrastructure project in England, the unique funding scheme means that whilst the borrowing will be undertaken by the public sector, the funding to repay the


88 | rail technology magazine Jun/Jul 14


Shaw noted that there have been some ‘challenges’ in trying to seek powers to build the extension. He said: “In the beginning I had to persuade people that we were going to build the railway and get the permission to operate it at the same time as trying to persuade the land owners to give up that land without knowing what we were going to build.


“We then had to try to secure the funding to build something that we didn’t really know what it was or when we could build it.”


But TfL did manage to persuade the GLA that it should borrow an “enormous” amount of money, Shaw said – but so far the unique funding process is “working extremely well”. Lots of people want to ensure the project is value for money, however.


Procurement


TfL has been conducting a procurement process which needed a “fi rm scope to be successful”.


In March 2013, TfL put out an OJEU notice for expressions of interest and that has been whittled down to four bidders: Balfour Beatty/ BAM, Bechtel/Strabag, Costain/Murphy and Laing O’Rourke/Ferrovial.


The two highest-scoring bidders are now participating in the next phase of the procurement process – understood to be Balfour Beatty/BAM and Laing O’Rourke/ Ferrovial, though TfL cannot confi rm this while the process is still underway.


Shaw said it was an interesting exercise to go to market to fi nd a contractor “and, in theory, place the contract before TfL had powers to build the railway”.


But he is confi dent TfL will award the contract in mid-to-late July and will receive the TWAO powers.


It is hoped the extension will improve transport links and public spaces in the local area and has been deemed “essential” to support the transformation of Vauxhall, Nine Elms and Battersea, a designated regeneration area on the South Bank.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148