This page contains a Flash digital edition of a book.
ELECTRIFICATION


Integrating advanced OLE works with the Reading Station Area Redevelopment


Richard Fluin explains how Tata Steel Project’s holistic approach to station redevelopment reduced the disruption of future OLE projects on commuters.


eading station is a key hub for passengers and freight, serving 14 million passengers per year – a number expected to double by 2030. Network Rail is near completion of a £850m redevelopment of the station including new platforms, track remodelling, a ‘transfer deck’ and new access structures.


R


Whilst the Reading Station Area Redevelopment (RSAR) was progressing, a significant opportunity arose to synergise future electrification of the route with the major enhancements being undertaken under RSAR. This recognised that the disruption to the customer during RSAR was significant – and that completing the station works, only to further disrupt passenger services as electrification followed, was unacceptable.


The impact of installing foundations, structural connections and steelwork installation could potentially have a significant impact on the civil engineering, buildings and systems infrastructure being installed. Integrating the two projects would reduce any potential for demolition and reconstruction of key station assets whilst installing critical OLE structures in the station area.


However, this was not only about negating customer impact; a key benefit to this approach was that access strategies in place to deliver RSAR could be utilised efficiently to deliver OLE installation and reduce future Great Western Electrification Programme (GWEP) requirements.


With these fundamental issues in mind, the RSAR team sought early funding from the electrification programme, supported by Tata Steel Projects (TSP), to assess the practicalities of a strategy to deliver the OLE structures in advance of GWEP and integrate it with their ongoing works. This decision was not without risk to the RSAR programme and delivery of the RSAR baseline remit; nonetheless the holistic view prevailed and the RSAR team set about developing an electrification delivery team under the RSAR project structure.


Design and engineering TSP


was already delivering the civil


engineering, M&E systems and track design for RSAR. As the incumbent designer co-located with the delivery team, this provided an ideal opportunity for TSP’s electrification team to become involved with the route electrification at project level.


Commencing work with RSAR in integrating a future programme of electrification was not without its challenges. Initially the focus was on accelerating the outline OLE design and assuring integration with the RSAR works. It is notable that at the time, much of the major station infrastructure works were either designed (or were actually being installed) prior to the electrification team’s engagement.


The full impact of the OLE foundation and steelwork design had to be understood and the interfacing solutions developed quickly and collaboratively: civil engineering infrastructure was modified or developed to make room for, or support, OLE foundations, masts, booms and other connections. This was managed successfully with minimal infrastructure modifications or rebuild required, and included:


• Station canopies • OLE foundations


• Connections to retaining walls • Integration with new elevated railway • Kennet Bridge supports


The installation programme was aligned to planned possessions; the procurement and installation programme was challenging and dynamic.


TSP mitigated the engineering risk by


engaging with the fabrication and installation contractors in the supply chain to ensure steelwork designs were both buildable and capable of manufacture – working with the installation team to understand the limitations of access and plant to develop the best solution


at each location.


Given the complex and high density of railway system infrastructure on the project footprint, there was a significant amount of bespoke design, which resulted in innovative and site specific design solutions, facilitated by the integrated design team with co-located designers in the project team throughout. This enabled rapid development of solutions as issues arose.


The result has been a significant success; whilst not commanding the caché of the Reading station building with its eye-catching, bold architectural design, the OLE structures have been installed with minimal disruption. OLE portals above the canopies were erected along with most of the main line structures east of the station where progress continues without disruption to the operational railway or the wider enhancement works.


This outcome illustrates what a dedicated electrification engineering team can achieve with strong experience in installation and understanding of the value of a functioning collaborative environment.


The professionalism of the team has contributed significantly to the successful delivery and highlighted TSP’s expertise in overhead line engineering.


FOR MORE INFORMATION


T: 019014 454600 E: tatasteelprojects@tatasteel.com W: www.tatasteelprojects.com


rail technology magazine Jun/Jul 14 | 51


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148