This page contains a Flash digital edition of a book.
ELECTRIFICATION


Pictured: Willow Park Autotransformer Feeder Station (ATFS)


Protection testing associated with the North West Electrification Autotransformer System – Phase 1


Ashley Jordan, testing and commissioning director for WJ Project Services Ltd, a ‘Level A’ nominated person on Network Rail’s infrastructure, has a detailed knowledge of the 25kV AC Overhead line system (both Autotransformer and Classic feeding arrangements) along with the 33kV / 750VDC traction system used widely in the south east.


he North West Electrifi cation Project – Phase 1 is part of a programme of works to install new OLE on the Chat Moss lines between Liverpool and Manchester and reinforce the electrifi cation infrastructure on the West Coast Main Line (WCML) at Newton-Le-Willows. The traction power supply system has been installed to a 12kA fault level 25kV – 0 – 25kV Autotransformer (AT) system. Phase 1 of the project involved the


T installation


of two new substations, Ordsall Lane Mid-Point Autotransformer Station (MPATS) and Willow Park Autotransformer Feeder


Station


(ATFS). The initial implementation was


protection is provided by Siemens Siprotec 7ST61 and Schneider P143 Relays.


The initial works included moving the


132/25kV railway in-feeds from the existing Parkside Feeder Station to the new Willow Park ATFS substation. This was followed by the transfer of all track feeders feeding the WCML during a nine-day blockade of the line.


The long-term plan is to use the 400kV/50kV/25kV derived supply from Weaver Junction ATFS on the WCML to provide a full AT supply to the Liverpool to Manchester scheme, as the WCML Phase 3B project works progresses.


Typical autotransformer feeding arrangement


limited to a 6kA fault level ‘AT lite’ system.


Testing and commissioning works associated with the new substation equipment involved using OMICRON CMC 353 / CMC 356 secondary injection equipment to carry out testing of the protection scheme, and has progressed to supporting the Network Rail Electrifi cation and Plant Design Group (EPDG) in setting the IEC 61850 standard, which is to be rolled out on future Network Rail projects.


Autotransformer system


The traction power supply system specifi cation called for a 12kA fault level 25kV – 0 – 25kV Autotransformer (AT) system, but with initial implementation as a 6kA fault level Autotransformer 25kV system (derived from the single phase 132kV/25kV incoming supply at Willow Park ATFS).


The two new autotransformer substations at Willow Park ATFS and Ordsall Lane MPATS are modular substation buildings with Siemens 8DA12 gas insulated switchgear. Willow Park ATFS is a 36 Panel Siemens 8DA12 substation. Ordsall Lane MPATS is a 26 Panel Siemens 8DA12


Substation. Circuit / equipment 46 | rail technology magazine Jun/Jul 14


Control is carried out using a conventional Siemens (formally Invensys) Supervisory Control and


Data Acquisition (SCADA) system, but it also has the capability of being controlled via the IEC 61850 network system functionality, which is being trialled in parallel.


Factory acceptance testing


During the FAT stage, WJ Project Services Ltd was brought in to support the testing of the modular substation arrangements. Particular areas of testing that were carried out were Current Transformer (CT) testing; Voltage Transformer (VT) testing; HV Pressure testing; and Contact resistance testing.


Time constraints during the FAT stage meant that the testing methods used needed to be effi cient. Due to other installation and testing works being carried out, there was limited access to the HV switchboard, which caused concern over the conventional CT testing methods the client had called for. From experience, carrying out separate ratio / polarity tests / magnetisation curves / resistance / knee point tests on the 122 protection CTs would have taken an estimated eight days of engineers’ labour. A further three days would also have been needed to process the results into a report format and plot the required magnetisation


Aside from saving considerable time, other benefi ts of using the CT Analyser were:


• •


Consistency in testing methods to achieve identical testing methods


Standardised test report format for all results


• Less room for error and retesting requirements


• •


• Accuracy of the test results


Traceability of the test results – being date and time stamped


Ensuring CTs were always left in a demagnetised state following testing


• Automatic CT Class identifi cation Site acceptance testing


Once the substation modules were transported and positioned at their fi nal locations, the SAT stage began. With little more than fi ve months


curves.


A quicker and more consistent CT testing method was needed, and from previous project works with Balfour Beatty and Babcock International, OMICRON’s CT Analyser was suggested to the client as a quick and effi cient solution. Although there were additional costs for the hire of the CT Analyser equipment, these were offset against the time saved in engineering resources.


The use of the CT Analyser reduced the testing time by some 40%, to an overall total of seven days for both the testing to be carried out and the reports to be printed for handover to the client.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148