This page contains a Flash digital edition of a book.
ELECTRIFICATION


• •


HV cable pressure testing Earthing system testing


During the SAT phase of the works, WJ Project Services Ltd used its own OMICRON CMC 353 secondary test set to carry out the testing of the protection scheme. The total number of protection devices across the two sites is summarised below:


Location


Relay Device Type


Schneider P143 Feeder Management


Siemens 7ST61 Distance Protection


Willow Park ATFS


31 20


Ordsall Lane MPATS


16 10


With 77 devices to apply settings to and test on site, it was necessary to undertake the testing using a consistent and clearly defined testing method. The advantages of using the OMICRON CMC 353 test set with the Test Universe software were that a pre-defined report format could be used to test each relay, from which records could be easily collated into the hand-back documentation and a custom report produced for each panel.


System testing – short circuits


from delivery to site though to energisation of the substations, the construction activity started with the installation of the 400mm2 HV cabling. Some 27km of HV cabling was required to cable the two substation buildings to the new and existing OLE infrastructure.


During the site commissioning, all disciplines needed to be inside the building together: construction pulling in and terminating HV cables, the switchgear connecting the two-part Willow Park ATFS busbar together, telecoms installing pilot circuits, and electricians installing the LV and control wiring to the external plant.


With this construction activity taking place, the SAT commissioning works needed to continue to achieve the incoming feeder transfer and energisation dates in July 2013. SAT consisted of the following:


• • • •


• • HV Pressure testing


Busbar Contact resistance testing Functionality testing of the switchgear


Application and secondary injection of final protection settings Autotransformer testing


• SCADA testing to the Network Rail Electrical Control Room (ECR) On site functional testing


On completion of the SAT phase one of the incoming feeders at Willow Park ATFS was commissioned into service and used to energise the new substation arrangement. This 25kV supply allowed the HV busbars / HV cables and autotransformers to be soak-tested over a 24- hour period. A further requirement was to carry out a short circuit test to prove the stability of the incoming protection scheme, and verify that the new Willow Park ATFS site met the BS- EN-50122 standards for rise of earth potential.


There had been concerns that due to the site being constructed on made-up ground, the earthing system would not perform as required. Thankfully, results showed rise of earth potentials within the limits defined by the standard.


With Network Rail acceptance, Willow Park ATFS was switched in to feed the WCML, replacing the old Parkside FS. Section proving was undertaken at the end of the WCML July 2013 blockade, and relay directional testing verified to prove the protection scheme on the Siemens 7ST61 relays.


Following on from the entry into service of Willow Park ATFS, the final connections of Ordsall Lane MPATS were undertaken to the newly installed overhead infrastructure on the Liverpool to Manchester lines. With this line


Further IEC 61850 Testing


In conjunction with the EPDG, the Willow Park ATFS to Ordsall Lane MPATS substation system, connected via optic fibre for IEC 61850 functionality, has been used as a test bed for developing the new Rationalised Auto Transformer Scheme (RATS). This system is being developed for use on the Great Western Electrification Project, whereby overhead line section circuit breakers will be kept to a minimum and, instead, load break switches will be installed. Under fault conditions, tripping of the entire system takes place with IEC 61850 protocol with Generic Object Oriented Substation Events (GOOSE) messaging used to isolate and reconfigure the overhead line system around the fault.


WJ Project Services Ltd is supporting Network Rail during the development of RATS, using dynamic testing techniques such as GPS- linked OMICRON secondary injection test equipment to simulate / inject simultaneous fault conditions at different site locations, to replicate and model overhead line tripping events and in turn see how the protection system will react.


About the author


Ashley Jordan (MEng (Hons) MIET) has more than 12 years of power distribution and commissioning experience, having worked on many of the UK’s large electrification projects. He is a Member of the IET and has a high level of practical and technical ability in project managing, planning, supervising, construction, maintenance


and repair of


Network Rail’s 25kV AC / 750DC, distribution, plant and OLE. He has worked most recently as commissioning manager for the North West Electrification – Phase 1 Autotransformer Project.


This paper was presented at the OMICRON Protection


Testing


Conference & Workshop in collaboration with ABB from 10-12 June 2014.


Ashley Jordan


opinion@railtechnologymagazine.com TELL US WHAT YOU THINK


rail technology magazine Jun/Jul 14 | 47


having never been electrified, it was necessary to carry out four short circuit tests to prove protection discrimination and immunisation of the existing signalling equipment against the new overhead line system.


This final system energisation and verification allowed the first Pendolino trains to begin running on the lines for driver training in November 2013.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148