[ Project focus: IBC ]


performance components and sub-assembly techniques. A factory-controlled environment improves overall quality, as products and systems can be fully checked, tested and signed-off prior to being delivered on site.


Fit for purpose Designer M&E Services UK has a vast amount of experience in working with modular systems and has installed them in many of its previous projects. Nick Baish explains: ‘Having previously used modular wiring systems in high profile jobs such as Wembley Stadium and Royal London Hospital, we invited Apex Wiring Solutions to put together and present a proposal for the IBC.’ Dave Lewis, managing director of Apex Wiring Solutions,


adds: ‘Our proposal was accepted and we started work with Designer M&E Services UK in August 2011 with a view to achieving completion and hand over by the end of March 2012. This is an enormous undertaking and one that only a company with our experience and expertise is able to fulfil.’ Apex is a market leader in the manufacture of modular systems, with a leading position in the UK healthcare market for electrical wiring products, supplying systems to more than 50 PFI and ProCure21 schemes. It also provided the London 2012 Olympic Village apartments with a fully pluggable modular scheme.


An aerial overview of the Main Media Complex, with the IBC central, and the Main Press Centre on the right


Game plan The IBC consists of more than 42,000m2


A factory- controlled environment improves overall quality, as products and systems can be fully checked, tested and signed off


of functional


space on two levels. The raw space within the IBC is allocated to the various 2012 Rights Holding Broadcasters (RHBs) by Olympic Broadcasting Services (OBS), the Host


Number crunching


Facts and figures about the Main Media Complex: n It took just 10 weeks to build the 4,500 tonne steel structure of the IBC, which is 275m long, 104m wide and 21m tall. That’s big enough to house five jumbo jets placed wing-tip to wing-tip.


n The IBC was the fifth building to be completed on the Olympic Park.


n There is a 200m long ‘high street’ with banks, newsagents, travel agents and a post office, plus a 12,000m2


catering village that will serve 50,000 meals per day. n It includes around 42,000m2 of functional space over


two double-storey floors, with a temporary gantry running along the building for technical equipment.


n All international images will be produced and distributed in HD format and broadcasting in 3D will be supported.


January 2012 ECA Today 33


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72