MECHANICAL CONTRACTING | PVF MARKET REPORT |


Market condition and activity bulletin-second quarter 2011


Stainless Steel Pipe Pricing:


another increase. Comments: One manufacturer


Stainless Steel pipe


pricing is expected to remain stable with lower surcharges offset by base price increases. Lead Times: Delivery lead times


are running 8-12 weeks, with fill rates of 20%-30%. Non-standard material delivery is out to 12-16 weeks. Comments: Inventories are


48


intentionally being kept lower due to price volatility. One manufacturer noted that deliveries move out slightly, then come back in after a week or two showing a very inconsistent order pattern. Some nickel alloy “remelt” grades are booked through the end of the year. Some industries are busier than others, leading to overall inconsistency in activity and pricing levels.


comments that commodity prices have remained at elevated levels with greater global demand than expected. PVF markets should be much stronger this year due to increased demand, higher prices, and oil prices soaring. There is too much capacity for both manufacturing and distribution. The master distributor has re-shaped the market structure and will continue to move into closer distribution channels with end-users. Another notes that it appears that business has improved slightly. Hopefully, this will continue. As prices rise, demand normally increases due to the fear of how high they may go. Pipe prices and the availability of plate and strip are the big issues effecting the stainless fitting and flange market. Everyone wants everything yesterday.


BY GARY


CARTWRIGHT PIPING AND


EQUIPMENT INC. Comments: Recently more than a


dozen U.S. Senators called for trade relief for U.S. steel producers, saying the industry is hurt by unfair practices by steelmakers in places such as Brazil, Japan and Russia. The senators are calling for relief for the U.S. steel industry, having sent a letter to the chairman of the U.S. International Trade Commission in advance of an April 6th , 2011 hearing to determine whether hot rolled steel imports from Brazil, Japan and Russia are having a negative impact on the domestic hot rolled steel industry. The senators claim several Ohio steel producers will be affected by the commission's decision including AK Steel Holding and Arcelor Mittal, steel pipe and tube producers that rely on U.S. hot rolled steel as their input to make pipe and tube. Among the other large U.S. steel producers are Pittsburgh based United States Steel Corporation and Charlotte based Nucor Corporation. The current steel market has been much more stable than in recent months. Manufacturers indicate it is unclear whether real demand will improve in the second quarter, or if destocking will offset any gains.


Stainless Steel Weld Fittings, 150 and Hi-Pressure Fittings


Pricing: (Weld Fitting 150#)


(SS Pressure Fittings) Manufacturers report increased prices from 3%-7- 1/2%. Nickel prices are up significantly and inventories reduced thus causing increased prices. Allegheny has gone up 7%-9% on strip for pipe. Surcharges for May will probably go back down to the March numbers; otherwise, the prices may have increased further. Labor and material costs have drastically risen in China and India with both countries having rapid growth and accompanied inflation. Lead Times: Fill rates are running


75% to 85% with lead times of 4-6 weeks for commodity domestic material and 8-12 weeks for import material not in stock. Look for deliveries to go out further due to pipe extended deliveries. Some mills over-booked at low prices and are now suffering from extended lead times. Nickel was on a steady rise, but then has dropped off a little. Due to the crisis in Japan, we may see


Stainless Steel Flanges Pricing: Manufacturers forecast


price increases averaging 5% for stainless steel flanges. Labor and material costs have drastically risen in China and India. Both countries have rapid growth and accompanied inflation. Lead Times: Fill rates are forecast


for 60%-75% with lead times of 4-6 weeks domestic and 8-12 weeks foreign. Specialty flanges are out 12- 16 weeks. Comments: Rising costs for raw


materials, supply, demand and reduced on hand inventories are causing increased prices. Nickel prices have risen significantly in the past year reflecting higher raw material prices.


Carbon Steel Pipe-Seamless, ERW and Continuous Weld


Pricing: Welded pipe has


increased 28% since January and seamless may be increasing soon. Lead Times: Fill rates are running


at 75%-90% with lead times of 8-12 weeks.


Carbon Steel Weld Fittings and Flanges


Pricing: One manufacturer


predicts pricing will remain stable through the second quarter on carbon steel fittings and forged steel flanges and another indicates an 8%- 10% increase in carbon flanges. However, due to the unstable world conditions unexpected changes could occur. Lead Times: Fill rates are running


90%-100% or more for fittings and flanges. Deliveries for material not in stock is forecast for 3-4 weeks. Non- stock specials are forecast for 6-8 weeks. Comments: Demand and stable


costs of raw materials have kept pricing stable or only rising slightly. While prices for raw forgings have risen somewhat, the rise has not precipitated an increase in pricing as of this writing. The 2011 market is expected to see demands similar to that of 2010. Most of the major construction projects will be funded by some form of government funding either at the local, state or federal level. The extension of the Bush Tax Rates


phc june 2011 www.phcnews.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88