IT’S ALL IN THE DETAIL F


Nico Röper looks at the necessary processes and reports required to deliver a refit paint project


irstly, corrosion protection and the cosmetic finish are for a large part dependent on the application properties of the chosen products. The wet paint in the can is only half of the final outcome, the other half being the application.


It is therefore vital to set a project up along the following lines: • Carry out a full pre-refit paint status survey • Prepare a bid book to reflect all necessary requirements • Have the yard / contractor prepare a paint manual • List responsibilities and communication lines • Have clear and open corporation between all parties


PRE-REFIT PAINT STATUS SURVEY


This document provides the facts, and includes a full report of the overall paint condition including a summary of any paint defects present, their quantities, density and locations.


BID BOOK


The bid book describes the full scope of work and specific requirements to remedy the types of defects that are present. A good bid book leaves no surprises, provides all necessary information to prepare quotations and enables the owner’s team to compare quotations from different parties. Some typical items addressed in a bid book are: • Scope of work and specifications for different areas of the vessel during the project


• General requirements that need to be fulfilled like tenting, scaffolding, protection


• Dates / planning requirements • Responsibilities of each party involved • Work methods / paint product requirements / certificate requirements / colour schemes


• QA/QC, inspection and reporting responsibilities • Reference areas or reference panel requirements • Technical and cosmetic acceptance criteria and parameters


PAINT MANUAL


The yard and paint contractor have the obligation to prove how all requirements will be fulfilled, processes controlled and agreed targets achieved. The paint manual includes a detailed description of the surface preparations, products, number of coats, application, specific conditions and parameters to be met.


SET UP INSPECTION, COMMUNICATION AND RESPONSIBILITIES It is vital that the paint contractor and yard have a quality management system in place and the responsibilities of each different inspection party are clearly described. In general this shall reflect the following set up: • The contractor will inspect, report and verify 100% of all work carried out


• The yard will verify all main steps of the process, document inspection findings and distribute these as described in the agreed inspection plan


• The paint manufacturer technical representative will carry out regular spot inspections, report and distribute


• The owner’s team paint consultant / inspector will carry out regular spot inspections and final cosmetic result inspections to verify the quality of the work


Finally, it is vital that there is professional corporation between the ship yard, paint applicator, manufacturer and the owner’s team. With one common goal of making sure agreed parameters, methods and quality goals are realistic and acceptable in the given situation for all parties involved.


When refit documentation and QA/QC procedures are set up, prepared and carried out in accordance with above descriptions, safety and security for all parties involved is provided.


For more details Tel: +31(0)10 26 81 495 or visit www.atlaspaintconsultants.com


ONBOARD | SPRING 2017 | 133


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152