This page contains a Flash digital edition of a book.
1.3 23


Project description / groundworks methodology


The proposed East Anglia ONE Onshore Cable Route is approximately 37km long and is shown on Figures 25.6.1 - 4. An indicative working width layout is shown in Diagram 1. See the Environmental Statement (ES) Volume 1, Chapter 4 Description of Development (November 2012) for detail.


24


The cables for East Anglia ONE would be installed in two parallel trenches. In addition four further trenches each containing two ducts would be installed for future projects. Construction activities would be undertaken within a temporarily fenced strip of land (the Preferred Onshore Cable Corridor) which would generally be no wider than 55m.


25


The Preferred Onshore Cable Corridor would be widened in certain locations in order to apply other special engineering techniques. In particular, this would be the case where cables would be required to be buried at greater than the normal trench depth, for example, where the route crosses a major watercourse using horizontal direct drill (HDD) techniques; this would also include construction consolidation sites (CCS).


26


The 55m Preferred Onshore Cable Corridor incorporates sufficient spacing between cable trenches to prevent cable overheating, plus room for temporary construction works. The latter incorporates storage space for excavated material (a 9m wide subsoil storage area and a 11m wide topsoil storage area) and a haul road (5.5m wide) for the safe passage of construction personnel and machinery alongside the cable trench.


27 Where necessary, the working width would be reduced in certain locations by applying a range of special engineering techniques that could include:


• •


• •


28 Using lower thermal resistivity backfill in the cable trench


Removing the spoil to a remote storage area, thereby negating the need to store spoil adjacent to the trenches Routing the haul road elsewhere


Moving the haul road onto the top of backfilled trenches


Thus the area of impact requiring pre-construction assessments and covered by this WSI includes 35m of the (55m total) Preferred Onshore Cable Corridor that would be subject to topsoil stripping (i.e. less the topsoil and subsoil bund locations), plus the wider areas required for HDD and CCS (hereafter ‘the 35m working width/HDD/CCS areas’).


Outline Written Scheme of Investigation: Archaeology and Cultural Heritage (Onshore) Rev 01


Page 8


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89