This page contains a Flash digital edition of a book.
EIA topic Operation


Change in project parameters (as applicable to each topic)


spillages


Impacts only likely from spillages, no change


Decommissioning


Impacts only likely from spillages, no change


Underwater Noise and Vibration and Electromagnetic Fields Note that this chapter provides technical information only which is used in receptor topic chapters


These will be avoided by adoption of standard mitigation, the risk will not increase.


These will be avoided by adoption of standard mitigation, the risk will not increase.


Phasing would mean that piling activities would potentially be undertaken over a longer period (noise)


Under the worst case there is one additional platform, therefore a slight increase in magnitude of effect.


Spill risk will not increase


Key changes in effect/s


Likely change in impact significance


Comment


Spill risk will not increase


The windfarm capacity remains up to 1200MW therefore the worst case scenarios previously considered (in terms of piling hammer energy and number of piling events) is unchanged


Potential for LFAC export cables, only HVDC assessed at PEI (EMF)


Benthic Ecology Construction


There are limited changes in the infrastructure required – in the worst case one additional offshore platform and extra cable within the windfarm.


Phasing does not involve any


Phase III Report June 2015


East Anglia THREE Offshore Windfarm Page 21


There are differences in the effects on EMF from alternating current


There will be greater overall footprint, disturbance of sediment (from cable installation therefore a slight increase in magnitude of effect.


EMF effects will be assessed in the Benthic Ecology and Fish Ecology chapters


Given the limited changes compared with the scale of the proposed project – limited changes in magnitude of effect will not change the significance of impacts.


The assessment will be updated to reflect any changes in piling timings (including potential cumulative impacts)


The chapter will be updated to include LFAC and any newly available information on EMF effects


The ES will update the assessment for the revised parameters.


Phasing will be discussed for construction impacts


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49