46


BUILDING FOR EDUCATION PROJECT REPORT


INTERFACES


Getting the interfaces right was essential to ensure the building was air-tight, with the Vapour Control Line between the external and internal facade particularly vital


One key aim of the design was to provide a building that is cheap to run


aluminium system has been used in the sports hall.


PROJECT DETAILS


Project: Portsmouth UTC Location: London Road, Portsmouth Construction cost: £10.4m Client: Portsmouth City Council Architect: Stride Treglown Contractor: BAM Construct Structural engineer: Ridge Client’s quantity surveyor: Mott MacDonald


Cladding & roof contractor: Kovara Windows contractor: Dudleys Brickwork contractor: GP Masonry Structural steelwork: H Young Secondary steel frame contractor: Hadleys


One key aim of the design was to provide a building that is cheap to run. To that end, an array of more than 100 PV panels on one section of the hot melt roof will provide around 15,000 kWh of electricity per annum. On the ground floor of the atrium there will also be underfloor heating.


“It will be super-efficient in terms of insu- lation and will be very economical in terms of fuel,” says Newman.


The biggest issue created for the construction team by Stride Treglown’s distinctive triangular design was in the brickwork, and the need for different angles on the joins.


Specialist contractor GP Masonry took away piles of the bricks supplied by Wienerberger to cut and cement pairs to create angles for the corners of the lower section of the exterior wall. “The key has been to have specified


WWW.ARCHITECTSDATAFILE.CO.UK


materials that are flexible enough,” says Newman, who adds: “In achieving the building’s form, it’s all about using tried and tested components getting the inter- faces right.”


Getting those interfaces right to ensure that the building was airtight was also essential with the, Vapour Control Line between the external and internal facade particularly vital. Crookes adds: “What does make a differ- ence is whether it’s sealed or not and where you can have problems is the interface between contractors.” Internally, those problems have been overcome through the creation of work zones. Specialist contractors are expected to have completed work in one zone before moving to another.


The interior design specifies a plaster- board system from BG and this is being erected as part of a fit-out programme, which began in January 2017 and will provide a gross internal area of 5,000 m2


.


The project is due for completion on 24 July 2017 and the first intake of students will arrive after the summer, as a revolution in schooling is evident inside and out at Portsmouth’s new UTC.


ADF MARCH 2017


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84