LEGAL EAGLES FRANCE – OFFSHORE WIND FARMS CALLS FOR TENDER


A second call for tender for offshore wind farms totalling up 1 GW of new capacity is currently ongoing in France.


The bids for the two projects located in Normandy (Le Tréport) and on the Atlantic coast (near the islands of Noirmoutier and Ile d’Yeu) are to be submitted by 29 November 2013 and the winning bidders should be selected in the first semester of 2014. The two projects are expected to be commissioned in 2021-2023.


FURTHER STEP FORWARD


This second call for tender is a step forward towards the achievement by France of its 2020 target of 6 gw offshore wind farms installed capacity. Given this target, its technically less challenging sites and a long term PPA with EDF, which compensates against the lower wind speed average, France is seen by some players as the only European offshore wind market offering tangible growth opportunities at the moment with genuine opportunities for diversification.


CONDITIONS


The conditions for this second call for tender are quite similar to the ones used by the French government for the first call for tender, although some lessons were learned from the first experience. By way of background, four projects are currently being developed as a result of the first call for tender. Three of them were awarded to the consortium composed of EDF En and Dong Energy (Courseulles, Fécamp and Saint nazaire, totalling up approx. 1,500 MW) and one to a consortium led by Iberdrola (Saint Brieuc).


TENDER SYSTEM DETAILS


Under the French offshore wind farms calls for tender system, the winning bidder is granted the right to develop a project and to enter into a 20-year term PPA with EDF, at a fixed price, determined in its bid. The requirements in relation to the bids are extremely complex, as bidders have to provide the intended


Such studies should allow the winning bidders to confirm their technological choices and their bid price. The State can withdraw the project if it determines at this stage that the winning bidder is no longer able to implement the project for the price proposed in its bid. Selected bidders can also withdraw in limited circumstances.


King & Spalding


industrial agreements with the main suppliers, showing that they have secured the supply of the main components and describe in detail the conditions for implementing the projects. Securing such commitments from the suppliers and giving such details in the implementing process at the bid stage proves difficult in practice.


CRITERIA


The criteria for rating the bids are the following: industrial organisation (40 pts/100), electricity purchase price (40 pts/100) and environment and social impact (20 pts/100). A maximum electricity purchase price is provided and bidders may try to reduce the price by submitting combined bids for the two projects.


TENDER SPECIFICATIONS


The Tender Specifications provide for an original feature, a 24- month period after the award (the ‘risk mitigation period’) (18 months in the first tender) during which the winning bidders shall carry out various studies (meteorological, geotechnical, geological, topological surveys, UXO assessment, etc).


www.windenergynetwork.co.uk


95


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116