ELECTRIFICATION & OLE


Electrifying the Great Western


Anne Watters, OLE technical manager at Amey, spoke at the IMechE electrification colloquium to explain the preparations for Great Western Main Line electrification.


In


March 2012, Amey was delivered the operate, deliver and maintain contract


from Network Rail for the GWML electrification project.


the project.


Watters said: “Obviously, for those quantities and the timescales, Network Rail has had to look at a totally different method of installation from the traditional install, which is where the High Output Plant System (HOPS) came in.”


The route is 191 miles, plus the stretch from Cardiff to Swansea, which is also to be electrified.


Network Rail ordered the £35m, 23-vehicle ‘factory train’ back in December 2011 from Windhoff Bahn- und Anlagentechnik GmbH. The machine, able to electrify an average of 1.6km of track per night, is making its real debut on the GWML this year.


Its three consists of trains, Watters explained: Consist 1a and 1b are for the foundations (piling and concrete respectively); Consist 2a is for the main steelwork; Consist 2b is for the SPS, auxiliary wiring and main line wiring; and Consist 3 is for the final works.


Watters said: “They’ll


Only 12 miles to Heathrow Junction are currently electrified, while Crossrail is carrying out the electrification from Stockley Junction as far as Maidenhead.


Anne Watters, OLE technical manager at Amey, told the IMechE electrification colloquium: “The project I’m part of is doing Maidenhead to Cardiff, including up to Oxford and down to Newbury, and then we will be looking at the extensions out to Swansea and potentially down to Basingstoke.”


There are three main phases to the project, she said – an initial 20-mile section of test track between Reading and Didcot by September 2015 to allow the IEP trains to be tested at line speed; then Maidenhead-Bristol by December 2016; and then Bristol-Cardiff by December 2017.


The panel gives an idea of the sheer scale of work and the quantities of materials needed for


72 | rail technology magazine Jun/Jul 13


work six nights a week; we’re moving away from just working on a Saturday night.


“They’ll work adjacent line open, meaning passenger trains can still run, so we get longer to work at nights.


“We’re not just working in the traditional four- hour white periods; we plan to have seven to eight hour possessions depending on the section of line.”


She explained that the original invitation to tender detailed a number of key requirements of the equipment, such as the ability to construct an average of one tension length of OLE per shift, and to transit in traffic at 60mph.


Watters’ presentation praised the Series 1 design by Furrer & Frey (pictured below), with its mono-anchor booms, single insulator cantilevers / registrations, a reduced number of components and reduced flaking of wires.


FOR MORE INFORMATION


http://www.networkrail.co.uk/aspx/12281. aspx


Scope of the work needed to electrify Maidenhead-Cardiff


• Three new National Grid supply points (and a further one for Crossrail’s section) • 30 autotransformer distribution sites • Approximately 1,000km of single-track • 16,000 pile foundations • Circa 14,000 OLE structures • 150+ structures to gauge clear • Four major tunnels, including the Severn Tunnel with its water ingress problems • One UNESCO World Heritage site at Bath


Ninety-two staff will work on HOPS, about three-quarters of whom will be new starters trained to OLEC competence, and the rest of whom will be existing OLE linesmen with additional Series 1 training.


© Windhoff Bahn- und Anlagentechnik GmbH


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100