This page contains a Flash digital edition of a book.
NEWS


ORR suggests cut of £2bn to Network Rail’s CP5 delivery plans


of around 40% achieved over the last two control periods.”


ORR chief executive Richard Price


(pictured left) said: “This


determination is stretching but achievable and it gives Network Rail incentives to build on past successes, and do even better than the challenges we have set.”


The ORR has said Network Rail should deliver its plans for CP5 for £2bn less than it had wanted.


In its Strategic Business Plan (SBP), Network Rail proposed spending £40.1bn on running and expanding the railways from 2014 to 2019, but the ORR, after extensive analysis, says the cost should be £37.9bn.


The ORR says that savings can be made through better use of new technology, more efficient ways of working and better management – but not at the expense of safety.


Below: CP4 spending (column 1), Network Rail’s proposal (column 2), and the ORR’s draft determination (column 3).


The ORR has criticised aspects of Network Rail’s submission, saying “a number of documents were submitted late and with significant inconsistencies”, but said overall the organisation had made “much more realistic assumptions about the cost reductions that could be achieved” compared to CP4.


The ORR said it had “largely protected Network Rail’s maintenance expenditure so that the delivery of a high-performing railway is not compromised”, while suggesting additional funding for civils upgrades and level crossings improvements and closures.


The ORR’s assessment suggests the day-to- day operational cost of running the network for CP5 should be £21.4bn.


It has proposed “tougher” regulatory targets, saying at least nine out of ten trains must run on time on each individual route.


Network Rail has said the ORR draft determination “needs careful and detailed thought” before it gives its formal response in September. A spokesman said: “Getting the balance right in making the choices between performance, growth and value for money is critical if we are to build on efficiency savings


The main £12bn enhancements programme has been approved, though the ORR wants to see better-developed plans before it releases funds for those still in the early stages of planning, which amounts to nearly £7bn worth of projects. £67m of funding to upgrade and close level crossings in England and Wales has been approved.


Below: A summary of the ORR’s expenditure assumptions compared to PR08, forecast CP4 outturn (adjusted to make it more comparable to this determination) and the SBP.


The ORR is “expecting Network Rail to deliver a further 20% efficiencies” in CP5, meeting the McNulty efficiency challenge.


But it says: “We have also carefully considered the lessons of CP4. When Network Rail tried to make efficiency savings in maintenance in CP4, it did not manage the change well in some respects.


“We have reduced the level of efficiency improvement required at the start of the control period for maintenance compared to Network Rail’s SBP to give the company more time to plan the necessary changes and implement them effectively. Effective delivery is essential if longer term efficiency gains and service quality improvements are to be secured and locked-in for the future.”


On access charges, the ORR estimates that in real terms the average total franchise passenger variable charges and open access variable charges will each increase by 1% from CP4 to CP5 in real terms.


To read the ORR’s draft determination, visit: www.rail-reg.gov.uk/pr13/consultations/draft- determination.php


Network Rail’s debt could be ‘unsustainable’


The ORR used the draft determination to raise the issue of Network Rail’s debt mountain and the cost of servicing it. It notes: “Network Rail’s debt is forecast to rise from £30,242m at the end of 2013-14 to £40,118m by 2019, although its assets will also grow in value. The rise in debt largely reflects the funding of renewals and the large enhancement programme.


“We forecast that Network Rail will spend on average around £1,200m a year servicing the debt in CP5. Under reasonable assumptions debt could continue to rise in future control


4 | rail technology magazine Jun/Jul 13


periods and there will need to be a debate within government and the industry about how sustainable this is.”


A similar point was made by Network Rail chairman Richard Parry-Jones in his Railtex 2013 speech. He said: “Much of [our] money comes from borrowing from the national bond market against our asset register. That’s great for awhile, but I don’t know if it’s ultimately infinitely sustainable.”


More from his speech on page 22.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100