LONDON UNDERGROUND


Innovation in tracklaying P


London Underground is embracing the adoption of high output track laying methods for its track renewal programme, taking advantage of the latest fastening technology from Pandrol. Wayne Peacock, sales and marketing manager for Pandrol UK highlights the benefi ts of the Pandrol system.


androl Fastclip was the world’s fi rst fully captive, self-tensioning, resilient rail


fastening. It is delivered to the tracklaying site pre-assembled on the sleeper, eliminating loose component distribution and handling on the track. The underlying principle of the Pandrol Fastclip is a ‘switch on/switch off’ one. It is a ‘total’ system – once the sleepers are laid and the rail installed, the clip is simply pushed onto the rail by means of a simple ‘drive’ action.


For de-stressing, the rail is quickly and easily released. The system is ‘switched off’ leaving the clip in a parked position, with all the components remaining captive on the sleeper.


This singular development in rail fastening technology has changed the way railway track is laid, de-stressed and maintained by enabling contractors to automate the entire tracklaying operation, and thus take advantage of the associated cost and time savings.


Increasing tracklaying productivity


The next stage was to look for areas where tracklaying


methods could be improved


further. Pandrol’s vision is to offer a system that can offer signifi cant savings not only in labour, but in valuable and costly possession


times. Working with two Pandrol subsidiary companies, this system incorporates:


- The pre-assembled Pandrol Fastclip rail fastening; - High output mechanised


installation equipment from Rosenqvist Rail; and


- Stressing rollers from Vortok International ... which working in combination offer a unique system for the highly effi cient installation and de- stressing of track.


Vortok International Vortok’s


latest development, the Vortok


Stressing Roller (VSR), assists in the rail stressing operation, ensuring the rail is safe both in extremely hot and in bitterly cold weather. It replaces less sophisticated techniques, which require three different pieces of equipment – an under-roller, a side-roller and a rail raising device.


The VSR combines the functions of all three of these pieces of equipment in one unit, resulting in savings in labour, time, and therefore costs.


Rosenqvist Rail


Rosenqvist Rail AB are specialists in the design, manufacture and marketing of high production machinery, equipment and working processes for the construction and maintenance of railway track.


The Rosenqvist CD400 clip driver is designed for use with a road/railer vehicle that can supply hydraulic power to the operating unit.


The clip driver can both install and extract


Fastclip fastenings, and can be combined with accessories for raising low-lying track sleepers if necessary. The unit is capable of achieving installations rates in the region of 40 sleepers per minute.


The Rosenqvist CD500 Hi-Output clipping machine is a self-propelled machine that uses a pincer method to insert or extract four Fastclip fastenings at a time.


The clipping function can operate, at choice, in manual, semi-automatic or fully-automatic modes, and in the latter mode, the machine can clip up fastenings at a rate of 70 sleepers per minute, with no intervention by the operator.


These three components – the Pandrol Fastclip rail fastening, Vortok Stressing Rollers, and Rosenqvist’s high-output track machinery – have placed Pandrol in a unique position to offer a system that offers maximum time and cost savings in the fi elds of tracklaying and maintenance.


FOR MORE INFORMATION


T: 01932 834500 W: Pandrol.com


rail technology magazine Jun/Jul 13 | 37


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100