This page contains a Flash digital edition of a book.
WORKSHIP EQUIPMENT & RAIL DEPOTS


T Investing to improve services


he effective maintenance of rolling stock is


becoming an increasingly important aspect of asset management and service improvement. It is therefore prudent for train operators to maintain as much investment as possible in the maintenance facilities. This is something National Express East Anglia understands.


“The need to renovate the train maintenance depot at Clacton-on-Sea originates from the HLOS (high level output statement) agreement with the Department for Transport,” says John Ratcliffe, engineering director at National Express East Anglia.


“In the early days of HLOS it was identified that East Anglia would need around 180 extra vehicles to cope with the forecast passenger growth over the current regulatory period. We then had to identify how we were going to cater for this additional rolling stock in terms of cleaning and maintenance.


“We began by taking a look at the existing facilities to see if we could meet the demand by working a bit harder and squeezing more performance out of those assets. Fairly quickly we identified we couldn’t do that, because the two main depots at Ilford and Norwich simply wouldn’t be able to cope with that extra volume of vehicles, which actually amounted to an increase of around 15 per cent.


“In the scheme of things this is fairly big increase and so we had to look at alternatives, including building new depots. In particular we focused on West Anglia, because some


Since being closed by a previous operator in the 1990s, the train maintenance depot at Clacton-on- Sea had been largely dormant until National Express East Anglia invested £1.5 million to bring the depot back to life. Rail Technology Magazine spoke to John Ratcliffe to find out more


“Then we looked at Clacton, which had the benefit of being on the NXEA network and whilst it was the right size it again needed extensive refurbishment works, because it had been run down in the mid-90s and had only been used in a piecemeal fashion by contractors ever since. This carried on until about 18 months ago, when the facility was vacated by its last owner and left in a complete state of disrepair.


“Although it required a lot of work, we decided to go and have a look at it. It was obvious it was in a pretty sorry state, although the main shed wasn’t too bad. Having said that, the main accommodation, storage area and facilities in general were completely dilapidated and the roofs had caved in. This meant the weather had got in and there was literally buddleia growing inside the depot buildings.


of the capacity - but not all of it - was coming through this area, operating through the Liverpool Street to Stansted and Cambridge route where we don’t have a maintenance facility.


“This meant one of the options we looked at quite early on was to build a brand new depot to service the new trains, with the older trains being maintained by the two existing depots. This plan proved not to be viable and too expensive, given the cost of a new depot - depending on how big it is and its location - can be


74 | rail technology magazine Dec/Jan 11


anywhere between £15 and £30 million.


“We simply couldn’t justify this expenditure to the Department for Transport, so we began to look at existing facilities. There were a number around the patch. One potential facility was a depot near Cambridge, which was fully operational and had become surplus to requirements. Unfortunately plans to improve access to that particular depot also proved too expensive, so the search continued.


“So at first glance we were a little concerned over the refurbishment costs, but when we looked into it in a bit more detail and had some further surveys done it became evident the cost of bringing it back into operational use was significantly less than it would have been to renovate any of the other depots we had seen.


“In the end it cost us £1.5 million, which is about ten per cent of the cost of a new facility and in our discussions with the Department for Transport it became very clear early on the project offered very good value for money.”


The utilisation of Clacton will be to mainly service trains which have been cascaded under the HLOS agreement.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92