This page contains a Flash digital edition of a book.
TRACK EQUIPMENT


Improving the network for everyone As the nation works to increase its productivity following the recession, it is essential that rail services


operate at their full capacity. A way of adding to that capacity is by enabling trains to run more quickly, reports Richard Mackillican


T


he rail network is the sum of many interconnected systems and when one of those systems is improved, it can lead to improvements on other parts of the network.


The gains felt by passengers following track improvement works to the Lafarge Rail Terminal at Mountsorrel provide a good example of how this can work.


Mark Tarry, area general


manager for Network Rail in the East Midlands, says: “For a while the junction between the Lafarge Rail Terminal at Mountsorrel and the Midland mainline has only allowed for a slow speed turnout at 5mph – which is pretty much as slow as you can move a train.


“That has led to quite a constraint – both on the terminal and on the mainline – because when a train is moving either from the mainline to the terminal or from the terminal to the mainline, we can not move other trains around, which is quite restrictive.


“So we needed to fi nd a way to help both the freight operators and the travelling public on the mainline with a solution that provided a win for everyone. That solution ended up being a relatively low-cost scheme, in railway terms, which increased the line speed by 10mph, to a 15mph limit.


“Whilst we knew the benefi ts would be signifi cant, they have turned out to be even more signifi cant than we expected.”


Before the improvement works could be carried out, the team


“Whilst we knew the benefi ts would be signifi cant, they have turned out to be even more signifi cant than we expected.”


had to assess the current track layout and determine what aspect of that layout was causing the low line speed and what needed to be done to increase that.


Given that a 5mph increase would have been a signifi cant increase in rail terms, a 10mph increase was going to present the team with a challenge.


Mark said: “We had to assess the infrastructure and in simple terms this involved lifting the track along with increasing the ballast underneath the track.


“This improves the gradient profi le which in turn allows the train to run at a higher speed.”


Although the work carried out was fairly standard stuff, the team still had a number of constraints to work to.


He said: “Given all of the current fi nancial constraints, this job probably wouldn’t have been of the highest priority across the network and this meant we had to carry the scheme out as cost effectively as we could.”


Although the team had to work hard to keep costs down, there were some signifi cant wins along the way.


“Firstly, we were able to get our in-house maintenance team to take on the whole job, which meant labour costs were signifi cantly lower than had we gone to the outside market.


“We were also lucky because Lafarge donated all of the materials free of charge as their contribution towards the job. Cont. overleaf


rail technology magazine Dec/Jan 11 | 37


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92